LAND BOUNDED BY EDGE OF NWL BRAN SANDS TREATMENT PLANT AND FORMER ICI LANDFILL TO SOUTH WEST; REDCAR BULK TERMINAL TO NORTH WEST LINE OF VEGETATION TOD POINT ROAD TO NORTH EAST AND EXISTING INTERNAL ROADS TO SOUTH EAST
Proposal
Discharge of condition 12 (Foul and Surface Water), 13 (Surface Water Maintenance), 15 (Remediation Scheme) and 23 (Floor Levels) following outline planning permission R/2020/0821/ESM for development of up to 464,515qm (gross) of general industry (Use Class B2) and storage or distribution facilities...
Application Type
Condition Discharge
Status
Valid
Parish(es)
Applicant
Teesworks
Applicant's Address
C/o Agent C/o Agent C/o Agent C/o Agent
Agent
Lichfields
Agent's Address
Mr Adrian Armstrong St Nicholas Building St Nicholas Street Newcastle upon Tyne NE1 1RF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
02/10/2026
Date Valid
02/10/2026
Expiry
27/11/2026
Consultation Expiry
-
associated_bldreg
-
Decision
-
Decision Date
-
Decision Level
-

Conditions table
# Condition Details
1 Prior to the commencement of any phase, a detailed scheme for the disposal of foul and surface water from that phase shall be submitted to and approved in writing by the Local Planning Authority in consultation with Northumbrian Water and the Lead Local Flood Authority. The scheme shall include the following: (i) The timetable and phasing for construction of the drainage system (ii) Details of any control structure(s) (iii) Details of surface water storage structures (iv) Measures to control silt levels entering the system and out falling into any watercourse during the construction process. The development shall, in all respects, be carried out in accordance with the approved Management Plan. the development shall be completed in accordance with the approved scheme. Thereafter the development shall take place in accordance with the approved details. REASON: To prevent the increased risk of flooding from any sources in accordance with the NPPF. REASON FOR PRE-COMMENCEMENT: A pre-commencement condition is required to ensure that excavations and groundworks do not compromise the installation of the approved surface water or foul drainage infrastructure.
2 Prior to the commencement of any phase or as approved as part of the phasing plan, details shall be submitted to and approved in writing by the Local Planning Authority of the Surface Water Management and Maintenance Plan applicable to that phase, unless otherwise agreed in writing. Thereafter it shall be implemented in accordance with the approved details. REASON: To ensure the development is supported by a suitably designed surface water disposal infrastructure scheme which is appropriately maintained and to minimise the risk flooding and contamination of the system during the construction process and in the locality minimise. REASON FOR PRE-COMMENCEMENT: A pre-commencement condition is required to ensure that excavations and groundworks do not compromise the installation of the approved surface water drainage infrastructure.
3 No development shall commence on each phase until a detailed Remediation Scheme to bring that phase to a condition suitable for the intended use (by removing unacceptable risks to human health, buildings and other property and the natural and historical environment) has been submitted to and approved in writing by the Local Planning Authority. The submitted scheme shall include a timetable for the works to take place. The development shall be carried out in accordance with the approved scheme, unless otherwise approved. Reason: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised.
4 Prior to the commencement of any phase of the development, or as otherwise approved through a phasing plan submitted under condition 5, full details of the finished floor levels for that phase shall be submitted to the Local Planning Authority for its written approval. The development shall be carried out in accordance with the approved details. REASON: To confirm the finished floor level of the development in the light of any necessary groundworks to meet the requirement of other planning conditions and confirm the overall height of the final scheme in the context of the information provided in the Environmental Statement. REASON FOR PRE-COMMENCEMENT: A pre-commencement condition is required so that the final agreed levels for the site are not compromised by the start of groundworks.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 406 kb 02/10/2026
Supporting Documentation
Remediation Design Statement Redacted (1) 9554 kb 02/10/2026
Covering Letter 263 kb 02/10/2026
Foundry Bellmouth - Road Markings – Layout 252 kb 02/10/2026
Foundry Bellmouth - Existing Utilities 356 kb 02/10/2026
Foundry Bellmouth - Traffic Signs – Layout 369 kb 02/10/2026
Foundry Bellmouth - Road Pavements – Layout 319 kb 02/10/2026
Foundry Bellmouth - Kerbs & Footways - Typical Details 262 kb 02/10/2026
Foundry Bellmouth - Surface Water Drainage – Catchment 584 kb 02/10/2026
Foundry Bellmouth – Contours 337 kb 02/10/2026
Foundry Bellmouth - Existing Layout 334 kb 02/10/2026
Foundry Bellmouth - General Arrangement (Colour) 1566 kb 02/10/2026
Foundry Bellmouth - Cabin Details 484 kb 02/10/2026
Foundry Bellmouth - Kerbs & Footways – Layout 414 kb 02/10/2026
Foundry Bellmouth - Surface Water Drainage – Layout 943 kb 02/10/2026
Consultee Name Date Letter Sent Consultation Expiry Date
Councillor N Bendelow (SOUTH BANK) 06/10/2026 -
Councillor S Jeffrey (SOUTH BANK) 06/10/2026 -
Engineers (Local Lead Flood Authority) 06/10/2026 -
Environmental Protection Team 06/10/2026 -
Northumbrian Water Ltd 06/10/2026 -