Location
Grangetown Prairie
Land east of John Boyle Road and west of Tees Dock Road
Grangetown
Proposal
Discharge of Condition 4 (Construction Management Plan) of outline permission R/2019/0767/OOM for the construction of an energy recovery facility (ERF) and associated development
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
Viridor Tees Valley Limited
Applicant's Address
Jutley
Ardley ERF
Middleton Stoney Road
Ardley
OXON
OX27 7AA
Agent
Viridor Tees Valley Limited
Agent's Address
Jutley
Ardley ERF
Middleton Stoney Road
Ardley
OXON
OX27 7AA
Agent's work phone
Agent's email
Case Officer
Mr A Miller
Case Officer Telephone
01287 612454
Case Officer Email
Adrian.Miller@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
24/02/2025
Date Valid
28/02/2025
Expiry
25/04/2025
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
28/04/2025
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | No development shall take place until a Construction Environmental Management Plan (CEMP) for the development has been submitted and approved in writing by the Local Planning Authority. The approved CEMP shall be adhered to throughout the construction phase and shall include of all those mitigation measures set out in Chapter 15 of Volume 1 of the submitted Environmental Impact Assessment December 2019 and Chapter 7 (Mitigation) of the Air Quality Assessment Rev 02 6 March 2020, unless alternative approaches to biodiversity and archaeology mitigation are submitted to and approved by the Local Planning Authority, in accordance with condition nos. 7 and 13, and thereafter carried out in the required timescales. In addition, the CEMP shall set out; i. The method to be used to control the emission of dust, noise and vibration from construction works, including any details of any mitigation measures required; ii. Measures to control the deposit of mud and debris on adjoining public highways iii. Site fencing and security iv. Temporary contractors’ buildings, plant, storage of materials, lighting and parking for site operatives v. The use of temporary generators vi. The arrangement or turning of vehicles within the site so that they may enter and leave in forward gear vii. A risk assessment of construction activities with potentially damaging effects on local ecological receptors including any measures to protect those receptors during construction viii. Roles and responsibilities for the implementation of the CEMP requirements and measures. REASON: To mitigate the impact of the development in accordance with the strategy set out in the Environmental Assessment. REASON FOR PRE-COMMENCEMENT: A pre-commencement condition is required as the environmental impact of the development will occur on the commencement of development. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 397 kb | 24/02/2025 | |
| Consultee Responses | |||
| Consultee response - Environmental Protection (Nuisance) | 240 kb | 24/03/2025 | |
| Decision | |||
| Decision Notice | 457 kb | 28/04/2025 | |
| Officer Report | |||
| Officer Report | 325 kb | 28/04/2025 | |
| Supporting Documentation | |||
| CEMP Attachment B Environmental Policy 2024 | 93 kb | 24/02/2025 | |
| CEMP Attachment A ISO Certificate | 1814 kb | 24/02/2025 | |
| Construction Phase Plan | 1698 kb | 24/02/2025 | |
| Preliminary Site Waste Management Plan | 454 kb | 24/02/2025 | |
| Construction Environmental Management Plan (CEMP) | 422 kb | 24/02/2025 | |
| Construction Traffic Management Plan (CTMP) | 2446 kb | 28/02/2025 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Councillor I Attwood (SOUTH BANK) | 04/03/2025 | - |
| Councillor N Bendelow (SOUTH BANK) | 04/03/2025 | - |
| Engineering Team (Highways) | 04/03/2025 | - |
| Environmental Protection Team | 04/03/2025 | - |
| Natural England | 04/03/2025 | - |
| South Tees Development Company | 04/03/2025 | - |