R/2025/0068/CD

Planning Application Details - Official Consultation has expired.

Location
LAND AT AND IN THE VICINITY OF THE FORMER REDCAR STEEL WORKS SITE REDCAR AND STOCKTON ON TEES TEESSIDE
Proposal
Discharge of Requirement 19 (Construction workers travel plan) in respect of Work Nos. 1, 7, 3B and 9A of the NZT DCO of reference number EN010103 for the Net Zero Teesside Order 2024 (the ‘Order’), which was made by the Secretary of State for the Department for Energy Security and Net Zero pursuant...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
Net Zero Teesside Power Limited
Applicant's Address
- c/o Agent (DWD Ltd) 69 Carter Lane London EC4V 5EQ
Agent
DWD Ltd
Agent's Address
MR ROBERT BOOTH 69 Carter Lane London EC4V 5EQ
Agent's work phone
Agent's email
Case Officer
Mr A Miller
Case Officer Telephone
01287 612454
Case Officer Email
Adrian.Miller@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
29/01/2025
Date Valid
29/01/2025
Expiry
26/03/2025
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
22/05/2025
Decision Level
Delegated

Conditions table
# Condition Details
1 Requierment 19 (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction workers travel plan for that part has been submitted to and, after consultation with National Highways and the relevant highway authority and STDC, approved by the relevant planning authority. (2) The plan submitted and approved must be in accordance with Chapter 16 of the environmental statement and the framework construction workers travel plan. (3) The plan submitted and approved must include— (a) measures to promote the use of sustainable transport modes to and from the authorised development by construction staff; (b) provision as to the responsibility for, and timescales of, the implementation of those measures; (c) details of parking for construction personnel within the construction sites; (d) a monitoring and review regime; and (e) the profile of activity across the day. (4) The approved plan must be implemented within three months of commencement of the relevant part of the authorised development and must be maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 409 kb 29/01/2025
Consultee Responses
Consultee Response - National Highways (1) 676 kb 20/02/2025
Consultee response - National Highways (2) 1024 kb 25/04/2025
Consultee response - National Highways (3) 154 kb 09/05/2025
Requirement 18 - Construction Traffic Management Plan (march 2025) Rev A02(1) 1077 kb 09/05/2025
Superseded
Requirement 19 - Construction Workers Travel Plan Mcc21001 257 A00 Xx Prm 10036 766 kb 29/01/2025
Requirement 19 - Construction Workers Travel Plan (march 2025) Rev A02 1067 kb 25/03/2025
Supporting Documentation
Covering Letter Final 218 kb 29/01/2025
Requirement 19 - Response To National Highways 194 kb 25/03/2025
Requirement 18 - Construction Traffic Management Plan Amended 25.04.2025 1102 kb 25/04/2025
Requirement 19 - Construction Workers Travel Plan (may 2025) Rev A04 971 kb 09/05/2025
Consultee Name Date Letter Sent Consultation Expiry Date
Engineering Team (Highways) 31/01/2025 -
National Highways 31/01/2025 -
National Highways 25/03/2025 -
South Tees Development Company 31/01/2025 -