R/2025/0067/CD

Planning Application Details - Official Consultation has expired.

Location
LAND AT AND IN THE VICINITY OF THE FORMER REDCAR STEEL WORKS SITE REDCAR AND STOCKTON ON TEES TEESSIDE
Proposal
Discharge of Requirement 18 (Construction traffic management plan) in relation to Work Nos. 1, 7, 3B and 9A of the NZT DCO of reference number EN010103 for theThe Net Zero Teesside Order 2024 (the ‘Order’), which was made by the Secretary of State for the Department for Energy Security and Net Zero ...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
Net Zero Teesside Power Limited
Applicant's Address
- c/o Agent (DWD Ltd) 69 Carter Lane London EC4V 5EQ
Agent
DWD Ltd
Agent's Address
MR ROBERT BOOTH 69 Carter Lane London EC4V 5EQ
Agent's work phone
Agent's email
Case Officer
Mr A Miller
Case Officer Telephone
01287 612454
Case Officer Email
Adrian.Miller@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
29/01/2025
Date Valid
29/01/2025
Expiry
26/03/2025
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
22/05/2025
Decision Level
Delegated

Conditions table
# Condition Details
1 Requirement 18 (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction traffic management plan for that part has been submitted to and, after consultation with National Highways and the relevant highway authority, STDC, Sembcorp, Royal Mail and the TG entities, approved by the relevant planning authority. (2) The plan submitted and approved must be in accordance with Chapter 16 of the environmental statement and the framework construction traffic management plan. (3) The plan submitted and approved must include— (a) details of the routes to be used for the delivery of construction materials and any temporary signage to identify routes and promote their safe use, including details of the access points to the construction site to be used by light goods vehicles and heavy goods vehicles; (b) details of the routing strategy and procedures for the notification and conveyance of abnormal indivisible loads, including agreed routes, the numbers of abnormal loads to be delivered by road and measures to mitigate traffic impact; (c) details of the activities to be undertaken to inform major users of highways in the area of the local highways authority about the impact of works to be undertaken to highways as part of the authorised development; (d) the construction programme, including the profile of activity across the day; (e) any necessary measures for the temporary protection of carriageway surfaces, the protection of statutory undertakers’ plant and equipment, and any temporary removal of street furniture; and (f) details of the monitoring to be undertaken in accordance with paragraph 16.5 of the framework construction traffic management plan. (4) Notices must be erected and maintained throughout the period of construction at every entrance to and exit from the construction site, indicating to drivers the approved routes for traffic entering and leaving the construction site. (5) The plan must be implemented as approved unless otherwise agreed with the relevant planning authority.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 408 kb 29/01/2025
Consultee Responses
Consultee Response - National Highways 676 kb 20/02/2025
Consultee response - Royal Mail 728 kb 24/02/2025
Consultee response - National Highways 1022 kb 25/04/2025
Consultee response - National Highways 154 kb 09/05/2025
Decision
Compliance Decision Notice 175 kb 22/05/2025
Superseded
Requirement 18 - Construction Traffic Management Plan (march 2025) Rev A02 1077 kb 25/03/2025
Supporting Documentation
Covering Letter Final 462 kb 29/01/2025
Requirement 18 - Response To National Highways 194 kb 25/03/2025
Requirement 18 - Construction Traffic Management Plan (march 2025) Rev A02(1) 1077 kb 09/05/2025
Requirement 19 - Construction Workers Travel Plan (May 2025) Rev A04 971 kb 09/05/2025
Consultee Name Date Letter Sent Consultation Expiry Date
- 31/01/2025 -
- 31/01/2025 -
Engineering Team (Highways) 31/01/2025 -
National Highways 31/01/2025 -
National Highways 25/03/2025 -
Royal Mail 05/02/2025 -
South Tees Development Company 31/01/2025 -