Location
DOGGER BANK WIND FARM C
ONSHORE CONVERTER STATION (OCS) AND ASSOCIATED WORKS NEAR LACKENBY NATIONAL GRID SUBSTATION
Proposal
Submission of details for Requirement 31 (1) and (2) (Light Emissions) in relation to Stage 9 for two offshore wind turbine generating stations and associated infrastructure in the Dogger Bank Zone and the Borough of Redcar and Cleveland. The full description of the authorised development is specifi...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
Dogger Bank Offshore Wind Farm Project 3 Projco Li
Applicant's Address
Dorothee Neun
1 Forbury Place
43 Forbury Road
Reading
RG1 3JH
Agent
Royal HaskoningDHV
Agent's Address
Claire Davies
Royal Haskoning D H V
53 Portland Street
Manchester
M1 3LF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
23/01/2025
Date Valid
23/01/2025
Expiry
20/03/2025
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
13/02/2025
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | 31.—(1) The Project A converter station works must not be brought into operation until a written scheme for the management and mitigation of artificial light emissions during the operation of the Project A converter station works has been submitted to and approved by the relevant planning authority. (2) The approved scheme for the management and mitigation of artificial light emissions for the Project A converter station works must be implemented and maintained during the operation of the Project A onshore works. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 415 kb | 23/01/2025 | |
| Consultee Responses | |||
| Consultee response - Environmental Protection (Nuisance) | 238 kb | 10/02/2025 | |
| Decision | |||
| Decision Notice | 452 kb | 13/02/2025 | |
| Officer Report | |||
| Officer Report | 304 kb | 13/02/2025 | |
| Supporting Documentation | |||
| Appendix B Drawings And Calculations | 9279 kb | 23/01/2025 | |
| Appendix A Consent Boundaries And Staging Plans Stage 9 | 1594 kb | 23/01/2025 | |
| Scheme For The Management And Mitigation Of Artificial Light Emissions Dco Stage 9 | 236 kb | 23/01/2025 | |
| Cover Letter | 154 kb | 23/01/2025 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Environmental Protection Team | 24/01/2025 | - |