Location
LACKENBY WORKS, REDCAR BULK TERMINAL LTD
TRUNK ROAD
REDCAR
Proposal
Discharge of Conditions 4 (Construction Surface Water Management Plan) and 5 (CEMP) of planning permission R/2023/0830/FFM for the remediation and strengthening works to the quay at Redcar Bulk Terminal
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
Southbay Civil Engineering Ltd
Applicant's Address
Moongate House
Fifth Avenue
Team Valley Industrial Estate
Gateshead
NE11 0HF
Agent
Southbay Civil Engineering Ltd
Agent's Address
Moongate House
Fifth Avenue
Team Valley Industrial Estate
Gateshead
NE11 0HF
Agent's work phone
Agent's email
Case Officer
Mr A Miller
Case Officer Telephone
01287 612454
Case Officer Email
Adrian.Miller@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
21/01/2025
Date Valid
21/01/2025
Expiry
18/03/2025
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
18/02/2025
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | Prior to the commencement of the development approved, or in such extended time as may be agreed in writing with the Local Planning Authority, details shall be submitted of a Construction Surface Water Management Plan and the development shall be implemented in accordance with the plan. REASON: In order to protect water quality in the adjoining Special Protection Area and Ramsar site during the construction process. |
| 2 | The development hereby permitted shall not be commenced until such time as a Construction Environment Management Plan (CEMP) has been submitted to, and approved in writing by, the Local Planning Authority. The scheme shall be implemented as approved. The plan should include, but not be limited to, the following: (a) Treatment and removal of suspended solids from surface water run-off during construction works; (b) Management of fuel, chemical, concrete and paint spills during construction, including the process in place to ensure the environment is not detrimentally impacted in the event of a spill; (c) Evidence and details of the physical barrier that will prevent surface water run-off from construction activities entering the River Tees. REASON This approach is supported by paragraph 180 of the National Planning Policy Framework (NPPF), which recognises that planning should contribute to and enhance the environment by preventing new and existing development from contributing to, being put at unacceptable risk from, or being adversely affected by, unacceptable levels of soil, air, water or noise pollution or land instability. Development should, wherever possible, help to improve local environmental conditions such as air and water quality, taking into account relevant information such as river basin management plans. This approach is also supported by the Planning Practice Guidance (PPG) for water supply, wastewater and water quality, which recognises that the Water Environment Regulations 2017 set out requirements to prevent the deterioration of aquatic ecosystems; protect, enhance and restore water bodies to ‘good’ status; and achieve compliance with standards and objectives for protected areas. The Northumbria River Basin Management Plan requires the restoration and enhancement of water bodies to prevent deterioration and promote recovery of water bodies. Without this condition, the impact could cause the deterioration of a quality element to a lower status class because it would result in the elevation of suspended sediments and hazardous substances. This could have significant implications for Water Framework Directive status and ecology. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 1171 kb | 21/01/2025 | |
| Consultee Responses | |||
| Consultee response - Environment Agency | 29 kb | 28/01/2025 | |
| Consultee response - Natural England | 21 kb | 06/02/2025 | |
| Consultee response - Engineers (Local Lead Flood Authority) | 449 kb | 17/02/2025 | |
| Decision | |||
| Compliance Decision Notice | 459 kb | 18/02/2025 | |
| Officer Report | |||
| Officer Report | 518 kb | 18/02/2025 | |
| Supporting Documentation | |||
| Conditions 4 & 5 - Environmental Risk Assessment | 330 kb | 21/01/2025 | |
| Conditions 4 & 5 - Environmental Management Plan | 1924 kb | 21/01/2025 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Councillor I Attwood (SOUTH BANK) | 22/01/2025 | - |
| Councillor N Bendelow (SOUTH BANK) | 22/01/2025 | - |
| Engineers (Local Lead Flood Authority) | 22/01/2025 | - |
| Environment Agency | 22/01/2025 | - |
| Natural England | 22/01/2025 | - |