Location
LAND AT AND IN THE VICINITY OF THE FORMER REDCAR STEEL WORKS SITE
REDCAR AND STOCKTON ON TEES
TEESSIDE
Proposal
Partial Discharge of Requirements 16(CEMP); 4(1)(Landscape and Biodiversity); 6(1)(External Lighting); 12(Flood Risk Mitigation); 15(Protected Species); 21(Noise) and 24(Waste Management) of reference number EN010103 for The Net Zero Teesside Order 2024 (the ‘Order’), which was made by the Secretary...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
Net Zero Teesside Power Limited
Applicant's Address
-
c/o Agent (DWD Ltd)
69 CARTER LANE
LONDON
EC4V 6AB
Agent
DWD LLP
Agent's Address
MR ROBERT BOOTH
69 CARTER LANE
LONDON
EC4V 5EQ
Agent's work phone
Agent's email
Case Officer
Mr A Miller
Case Officer Telephone
01287 612454
Case Officer Email
Adrian.Miller@redcar-cleveland.gov.uk
Consultation Start
06/01/2025
Weekly List Expiry Date
-
Date Received
24/12/2024
Date Valid
24/12/2024
Expiry
18/02/2025
Consultation Expiry
27/01/2025
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
08/05/2025
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction environmental management plan for that part has been submitted to and, after consultation with the Environment Agency, Sembcorp and STDC, approved by the relevant planning authority. (2) The plan submitted and approved must be in accordance with the framework construction environmental management plan and the indicative landscape and biodiversity strategy and incorporate— (a) a code of construction practice, specifying measures designed to minimise the impacts of construction works; (b) a scheme for the control of any emissions to air; (c) a soil management plan; (d) a sediment control plan; (e) a scheme for environmental monitoring and reporting during the construction of the authorised development, including measures for undertaking any corrective actions; (f) a scheme for the notification of any significant construction impacts on local residents and businesses for handling any complaints received relating to such impacts during the construction of the authorised development; (g) surface and foul water drainage measures that are in accordance with the surface and foul water drainage scheme submitted under requirement 11(1); (h) the measures outlined in paragraphs 15.7.4, 15.8.12 to 15.8.16, 15.8.19 and 15.9.1 in Appendix B: Ornithology in the Environmental Statement Addendum – Volume I of the ES addendum or such other measures to achieve the same maximum noise levels as are set out in paragraphs 15.8.13 to 15.8.16 of Appendix B: Ornithology in the Environmental Statement Addendum – Volume I of the ES addendum; (i) a groundwater monitoring plan that comprises monitoring of groundwater levels and chemical contaminants of concern to inform the construction design process and which must take into account the updated hydrogeological impact assessment and any further ground investigation reports and groundwater monitoring required by requirement 13(2)(f); (j) a materials management plan in accordance with paragraph 5.3.76 of Chapter 5 of the environmental statement; (k) a hazardous materials management plan in accordance with paragraph 10.5.3 in Chapter 10 of the environmental statement; and (l) any other management or mitigation plans set out in the framework construction environmental management plan. (3) All construction works associated with the authorised development must be carried out in accordance with the relevant approved construction environmental management plan unless otherwise agreed with the relevant planning authority. |
| 2 | (1) No part of the authorised development may commence until a landscape and biodiversity protection plan for that part has been submitted to and approved by the relevant planning authority (following consultation with Sembcorp and STDC). (2) The plan submitted and approved pursuant to sub-paragraph (1) must include details of— (a) measures to protect existing shrub and tree planting that is to be retained; (b) details of any trees and hedgerows to be removed; and (c) biodiversity and habitat mitigation and impact avoidance. (3) The plan submitted and approved pursuant to sub-paragraph (1) must be implemented as approved throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority. |
| 3 | (1) No part of the authorised development may commence, save for the permitted preliminary works, until a scheme for all external lighting to be installed during construction for that part (with the exception of the aviation warning lighting required by virtue of requirement 27) has been submitted to and approved by the relevant planning authority. (3) The schemes submitted and approved pursuant to sub-paragraphs (1) and (2) of this requirement must be in accordance with the indicative lighting strategy and include measures to minimise and otherwise mitigate any artificial light emissions. (4) The schemes must be implemented as approved unless otherwise agreed with the relevant planning authority. |
| 4 | (1) No part of the authorised development may commence, save for the permitted preliminary works, until a scheme for the mitigation of flood risk during construction, has, for that part, been submitted to, and after consultation with the Environment Agency and STDC, approved by the relevant planning authority. (2) The scheme approved pursuant to sub-paragraph (1) must be implemented as approved and maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority. (3) No part of the authorised development may be commissioned until a scheme for the mitigation of flood risk during operation has, for that part, been submitted to and, after consultation with the Environment Agency and STDC, approved by the relevant planning authority. (4) The schemes submitted and approved pursuant to sub-paragraphs (1) and (3) of this requirement must be in accordance with the principles set out in Chapter 9 and appendix 9A of the environmental statement. (5) The scheme approved pursuant to sub-paragraph (3) must be implemented as approved and maintained throughout the operation of the relevant part of the authorised development unless otherwise agreed with the relevant planning authority. (6) The authorised development must not be commissioned until the flood risk mitigation has been implemented and a flood emergency response and contingency plan has been submitted to, and after consultation with the Environment Agency and STDC, approved by the relevant planning authority. (7) The plan approved pursuant to sub-paragraph (6) must be implemented throughout the commissioning and operation of the relevant part of the authorised development unless otherwise agreed with the relevant planning authority. |
| 5 | (1) No part of the authorised development may commence until further survey work for that part has been carried out to establish whether any protected species are present on any of the land affected, or likely to be affected, by that part of the authorised development. (2) Where a protected species is shown to be present, no authorised development of that part must commence until a scheme of protection and mitigation measures has been submitted to and, following consultation with Natural England, approved by the relevant planning authority. (3) The authorised development must be carried out in accordance with the approved scheme unless otherwise agreed with the relevant planning authority. (4) In this requirement, “protected species” has the same meaning as in regulations 42 and 46 of the Conservation of Habitats and Species Regulations 2017(a). |
| 6 | (1) No part of the authorised development may commence, save for the permitted preliminary works, until a scheme for the monitoring and control of noise during the construction of that part of the authorised development has been submitted to and approved by the relevant planning authority, following consultation with Sembcorp. (2) The scheme submitted and approved must be in accordance with the principles set out in Chapter 11 of the environmental statement and specify— (a) each location from which noise is to be monitored; (b) the method of noise measurement; (c) the maximum permitted levels of noise at each monitoring location to be determined with reference to the ABC Assessment Method for the different working time periods, as set out in BS 5228-1:2009+A1:2014, unless otherwise agreed in writing with the relevant planning authority for specific construction activities; (d) provision as to the circumstances in which construction activities must cease as a result of a failure to comply with a maximum permitted level of noise; and (e) the noise control measures to be employed. (3) The scheme must be implemented as approved unless otherwise agreed with the relevant planning authority. |
| 7 | (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction site waste management plan for that part has been submitted to and, after consultation with STDC, approved by the relevant planning authority. (2) The plan submitted under sub-paragraph (1) must be in accordance with the framework site waste management plan. (3) The plan must be implemented as approved unless otherwise agreed with the relevant planning authority. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| - | 15/01/2025 | - |
| Engineering Team (Highways) | 06/01/2025 | - |
| Engineers (Local Lead Flood Authority) | 06/01/2025 | - |
| Environment Agency | 06/01/2025 | - |
| Environmental Protection Team | 06/01/2025 | - |
| Greener Future - Climate Change | 06/01/2025 | - |
| Natural England | 06/01/2025 | - |
| Northumbrian Water Ltd | 06/01/2025 | - |
| South Tees Development Company | 06/01/2025 | - |
| Address | Date Sent | Date Reconsulted | Expiry Date |
|---|---|---|---|
| WILTON INTERNATIONAL MIDDLESBROUGH TS90 8WS | 06/01/2025 | - | 27/01/2025 |