Proposal
Certificate of Lawful Existing Use or Development with regards to the Tees Combined Cycle Power Plant (‘CCPP’) which is subject to the Tees CCPP Development Consent Order (‘DCO’) 2019 (which came into force on 26 April 2019)
Application Type
Certficate of Lawfulness
Status
Approved
Parish(es)
Applicant
Sembcorp Utilities (UK) Limited
Applicant's Address
Sembcorp Utilities (UK) Limited
Agent
Lichfields
Agent's Address
Nicki Mableson
The Minster Building
21 Mincing Lane
London
EC3R 7AG
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
30/07/2024
Date Valid
30/07/2024
Expiry
24/09/2024
Consultation Expiry
-
associated_bldreg
-
Decision
GRANT CERTIFICATE OF LAWFULNESS
Decision Date
12/09/2024
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | The applicant has demonstrated that works have been undertaken that constitute a commencement of development prior to 26 April 2024. These works include: 1 Site clearance including removal of vegetation within the Order Limits; 2 The erection of temporary construction fencing as defined on the attached plan ‘Preliminary Works Phase A Fencing Plan’ (Ref: CCPP-PH-A-0007 Rev P1, dated Feb 2024); 3 Initial trenching to facilitate the future connection of power from existing sub-stations to the generating units as defined in Work No 1 of the Tees CCPP DCO and defined as Works No 1A – Power Station Complex and shown on the ‘Indicative Electrical Connection Plan Sheet 1 of 1’ Ref.GIS-00-L-02695 Rev 1, dated 9/11/17. The location of the initial trenching was shown on the following plans:- a ‘Preliminary Works Phase A General Arrangement’ (ref: CCPP-PH-A-0011 Rev P1, dated February 2024); b ‘Preliminary Works Phase A Greystones A Trench’ (ref: CCPP-PH-A-0014 Rev P2, dated February 2024); c ‘Preliminary Works Phase A Greystones B Trench’ (ref: CCPP-PH-A-0015 Rev P1, dated February 2024); and 4 Clearance of hardstanding within the area of the site to be occupied by Building 2: ‘Control Building’ approved as part of the Tees CCPP DCO (also marked on the ‘Indicative Electrical Connection Plan Sheet 1 of 1’ Ref. GIS-00-L-02695 Rev 1, dated 9/11/17) and the conducting of initial ground investigations through the carrying out of two borehole tests. Area being cleared through the breaking up of an existing exposed foundation slab shown on attached Plan ‘Preliminary Works Phase A Building 2 Enabling’ (ref: CCPP-PH-A-0021 Rev P1, dated February 2024). The Local Planning Authority therefore confirms that a lawful implementation of the Tees Combined Cycle Power Plant (‘CCPP’) which is subject to the Tees CCPP Development Consent Order (‘DCO’) 2019 has taken place. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 323 kb | 30/07/2024 | |
| Decision | |||
| Lawful Development Certificate | 2096 kb | 12/09/2024 | |
| Location Plan | |||
| Location Plan | 1973 kb | 30/07/2024 | |
| Officer Report | |||
| Officer Report | 232 kb | 12/09/2024 | |
| Supporting Documentation | |||
| Weekly Commissioning Report Week 17 | 4438 kb | 30/07/2024 | |
| Weekly Commissioning Report Week 18 | 7404 kb | 30/07/2024 | |
| Tees Combined Cycle Power Plant Order 2019 | 323 kb | 30/07/2024 | |
| Weekly Commissioning Report Week 16 | 4427 kb | 30/07/2024 | |
| Weekly Commissioning Report Week 16 | 5968 kb | 30/07/2024 | |
| TCCP Commencement Of Development Letter | 434 kb | 30/07/2024 | |
| Photographic Chronology | 7495 kb | 30/07/2024 | |
| Covering Letter | 197 kb | 30/07/2024 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Councillor C Cawley (DORMANSTOWN) | 30/07/2024 | - |
| Councillor D Powlay (DORMANSTOWN) | 30/07/2024 | - |