R/2023/0816/CD

Planning Application Details - Official Consultation has expired.

Location
LAND TO EAST FORMER STEEL HOUSE AND NORTH OF A1085 TRUNK ROAD REDCAR
Proposal
PARTIAL DISCHARGE OF CONDITION 7 (Part (a) and Part (B)(CONTAMINATED LAND) ON PLANNING APPROVAL R/2022/0816/FFM FOR FORMATION OF HARDSTANDING, BUILDINGS, ACCESS ROADS FROM A1085 TRUNK ROAD, ASSOCIATED FACILITIES AND LANDSCAPING WORKS IN ASSOCIATION WITH THE CREATING OF A PARK AND RIDE FACILITY
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
SOUTH TEES DEVELOPMENTS LIMITED
Applicant's Address
. ST NICHOLAS BUILDING ST NICHOLAS' ST - NEWCASTLE UPON TYNE - NE1 1TH
Agent
Lichfields
Agent's Address
MISS OLIVIA POWELL ST NICHOLAS BUILDING ST NICHOLAS' ST NEWCASTLE UPON TYNE NE1 1RF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
01/12/2023
Date Valid
01/12/2023
Expiry
10/01/2025
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
08/01/2025
Decision Level
-

Conditions table
# Condition Details
1 Unless an alternative phasing is agreed by the Local Planning Authority in writing, development other than that required to be carried out as part of an approved scheme of remediation must not commence until parts (a) to (c) have been complied with. If unexpected contamination is found after development has begun, development must be halted on that part of the site affected by the unexpected contamination to the extent specified by the Local Planning Authority in writing until condition (d) has been complied with in relation to that contamination. (a) Site Characterisation An investigation and risk assessment, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, whether or not it originates on the site. The contents of the scheme are subject to the approval in writing of the Local Planning Authority. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) an assessment of the potential risks to: • human health, • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, • adjoining land, • groundwaters and surface waters, • ecological systems, • archaeological sites and ancient monuments; (iii) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with Environment Agency’s Land Contamination Risk Management Guidance (b) Submission of Remediation Scheme A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. (c) Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority in accordance with an alternative phasing scheme. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. (d) Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of part (a) and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of part (b), which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to land contamination details which are often the first works on site and relate to site preparation.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form Amended 30.10.2024 - kb 30/10/2024
Updated Cover Letter October 2024 - kb 30/10/2024
Consultee Responses
Consultee response - Environmental Protection (Contaminated Land) - kb 19/12/2023
Consultee response - Environmental Protection (Contaminated Land) - kb 23/12/2024
Decision
Compliance Decision Notice - kb 08/01/2025
Officer Report
Compliance Officer Report - kb 08/01/2025
Superseded
Application Form - kb 01/12/2023
Cover Letter - kb 01/12/2023
Supporting Documentation
Con. No.7 - Phase 1 Contaminated Land Desk Study Part6 - kb 01/12/2023
Con. No.7 - Phase 1 Contaminated Land Desk Study Part7 - kb 01/12/2023
Con. No.7 - Phase 1 Contaminated Land Desk Study Part8 - kb 01/12/2023
Con. No.7 - Phase 1 Contaminated Land Desk Study Part9 - kb 01/12/2023
Con. No.7 - Phase 1 Contaminated Land Desk Study Part1 - kb 01/12/2023
Con. No.7 - Phase 1 Contaminated Land Desk Study Part2 - kb 01/12/2023
Con. No.7 - Phase 1 Contaminated Land Desk Study Part3 - kb 01/12/2023
Con. No.7 - Phase 1 Contaminated Land Desk Study Part4 - kb 01/12/2023
Con. No.7 - Phase 1 Contaminated Land Desk Study Part5 - kb 01/12/2023
Detailed Quantitative Risk Assessment Part1 - kb 30/10/2024
Detailed Quantitative Risk Assessment Part2 - kb 30/10/2024
Detailed Quantitative Risk Assessment Part3 - kb 30/10/2024
Generic Quantitative Risk Assessment Part1 - kb 30/10/2024
Generic Quantitative Risk Assessment Part2 - kb 30/10/2024
Generic Quantitative Risk Assessment Part3 - kb 30/10/2024
Generic Quantitative Risk Assessment Part4 - kb 30/10/2024
Generic Quantitative Risk Assessment Part5 - kb 30/10/2024
Generic Quantitative Risk Assessment Part6 - kb 30/10/2024
Generic Quantitative Risk Assessment Part7 - kb 30/10/2024
Generic Quantitative Risk Assessment Part8 - kb 30/10/2024
Generic Quantitative Risk Assessment Part9 - kb 30/10/2024
Generic Quantitative Risk Assessment Part10 - kb 30/10/2024
Generic Quantitative Risk Assessment Part11 - kb 30/10/2024
Generic Quantitative Risk Assessment Part12 - kb 30/10/2024
Generic Quantitative Risk Assessment Part13 - kb 30/10/2024
Generic Quantitative Risk Assessment Part14 - kb 30/10/2024
Generic Quantitative Risk Assessment Part15 - kb 30/10/2024
Generic Quantitative Risk Assessment Part16 - kb 30/10/2024
Generic Quantitative Risk Assessment Part17 - kb 30/10/2024
Generic Quantitative Risk Assessment Part18 - kb 30/10/2024
Generic Quantitative Risk Assessment Part19 - kb 30/10/2024
Generic Quantitative Risk Assessment Part20 - kb 30/10/2024
Generic Quantitative Risk Assessment Part21 - kb 30/10/2024
Generic Quantitative Risk Assessment Part22 - kb 30/10/2024
Generic Quantitative Risk Assessment Part23 - kb 30/10/2024
Generic Quantitative Risk Assessment Part24 - kb 30/10/2024
Generic Quantitative Risk Assessment Part25 - kb 30/10/2024
Generic Quantitative Risk Assessment Part26 - kb 30/10/2024
Generic Quantitative Risk Assessment Part27 - kb 30/10/2024
Generic Quantitative Risk Assessment Part28 - kb 30/10/2024
Generic Quantitative Risk Assessment Part29 - kb 30/10/2024
Generic Quantitative Risk Assessment Part30 - kb 30/10/2024
Generic Quantitative Risk Assessment Part31 - kb 30/10/2024
Generic Quantitative Risk Assessment Part32 - kb 30/10/2024
Generic Quantitative Risk Assessment Part33 - kb 30/10/2024
Generic Quantitative Risk Assessment Part34 - kb 30/10/2024
Generic Quantitative Risk Assessment Part34 Part1 - kb 30/10/2024
Generic Quantitative Risk Assessment Part34 Part2 - kb 30/10/2024
Generic Quantitative Risk Assessment Part34 Part3 - kb 30/10/2024
Generic Quantitative Risk Assessment Part36 - kb 30/10/2024
Generic Quantitative Risk Assessment Part37 - kb 30/10/2024
Remediations Options Appraisal Part3 - kb 30/10/2024
Remediations Options Appraisal Part1 - kb 30/10/2024
Remediations Options Appraisal Part4 - kb 30/10/2024
Remediations Options Appraisal Part2 - kb 30/10/2024
Consultee Name Date Letter Sent Consultation Expiry Date
Councillor C Cawley (DORMANSTOWN) 01/12/2023 -
Councillor D Powlay (DORMANSTOWN) 01/12/2023 -
Councillor I Attwood (SOUTH BANK) 01/12/2023 -
Councillor N Bendelow (SOUTH BANK) 01/12/2023 -
Environmental Protection Team 04/12/2024 -
Environmental Protection Team 01/12/2023 -