Location
LAND WEST OF KIRKLEATHAM LANE
REDCAR
Proposal
DISCHARGE OF CONDITIONS 6 (PLAY EQUIPMENT), 7 (PHASING), 8 (TRAFFIC MANAGEMENT PLAN), 9 (DRAINAGE), 10 (LLFA 1),11 (LLFA 2), 12 (CEMP) AND 13 (LEVELS) OF OUTLINE PLANNING APPLICATION R/2021/0019/OOM FOR RESIDENTIAL DEVELOPMENT WITH ASSOCIATED ACCESS, LANDSCAPING AND OPEN SPACES CONSISTING OF;
A) 27...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
COUNTRYSIDE PARTNERSHIPS NE
Applicant's Address
MR DAVID SCRIMGEOUR
2 ESH PLAZA
SIRBOBBY ROBSON WAY,
GREAT PARK
NEWCASTLE UPON TYNE
NE13 9BA
Agent
COUNTRYSIDE PARTNERSHIPS NE
Agent's Address
MR DAVID SCRIMGEOUR
2 ESH PLAZA
SIRBOBBY ROBSON WAY,
GREAT PARK
NEWCASTLE UPON TYNE
NE13 9BA
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
10/10/2023
Date Valid
10/10/2023
Expiry
11/04/2024
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
10/04/2024
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | The details submitted pursuant to Condition 1 shall include full details of play equipment located throughout the site. The play area shall be provided in accordance with the agreed phasing plan. REASON: To ensure a satisfactory form of development and for the avoidance of doubt. |
| 2 | No part of the development hereby permitted shall be implemented until a Phasing Plan for the timing and delivery of the development, in terms of the relationship between the phases of development and the proposed infrastructure, has been submitted to and approved in writing by the local planning authority. The development shall be undertaken in accordance with the Phasing Plan. REASON: To ensure a satisfactory form of development. |
| 3 | Prior to the commencement of each phase of development, a traffic management plan for the construction phased of the development shall be submitted to and agreed in writing with the Local Planning Authority. The scheme hereby approved shall then be implemented in accordance with the (traffic management/travel/transport*) plan unless first agreed in writing with the Local Planning Authority. REASON: To ensure that the development does not have an adverse impact on the highway network in accordance with policy SD4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as the information relates to construction activity and site preparation. |
| 4 | Development shall not commence on each phase of development until a detailed scheme for the disposal of foul water from the phase of development hereby approved has been submitted to and approved in writing by the Local Planning Authority in consultation with Northumbrian Water and the Lead Local Flood Authority. Thereafter the development shall take place in accordance with the approved details. REASON: To prevent the increased risk of flooding from any sources in accordance with the NPPF. |
| 5 | Prior to the commencement of any phase of development, or in such extended time as may be agreed in writing with the Local Planning Authority, details shall be submitted and approved of the surface water drainage scheme and the phase of development shall be completed in accordance with the approved scheme. The design of the drainage scheme shall include; i. Details of the proposed drainage system discharging into the existing strategic attenuation facility as approved under local planning authority reference number R/2019/0523/CD dated 31/10/19. This system is to be provided with sufficient storage within the system to accommodate a 1 in 30 year storm. ii. The design shall also ensure that storm water resulting from a 1 in 100 year event, plus climate change surcharging the system, can be stored on site with minimal risk to persons or property and without overflowing into drains, local highways or watercourses ii. Full Micro Drainage design files (mdx files) including a catchment plan iii.The flow path of flood waters for the site as a result on a 1 in 100 year event plus climate change Reason - To ensure the development is supported by a suitably designed surface water disposal infrastructure scheme and to minimise the risk flooding in the locality. |
| 6 | Prior to the commencement of any phase of development, or in such extended time that may be agreed with the Local Planning Authority, details of a Surface Water Drainage Management Plan shall be submitted and approved by the Local Planning Authority. The Management Plan shall include; (i) The timetable and phasing for construction of the drainage system (ii) Measures to control silt levels entering the system and out falling into any watercourse during the construction process The development shall, in all respects, be carried out in accordance with the approved Management Plan. Reason - To ensure the development is supported by an appropriately designed surface water disposal infrastructure scheme and to minimise the risk of increased flooding and contamination of the system during the construction process. |
| 7 | Prior to construction of foundations on any phase of development a Construction Environmental Management Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide the following; i) The parking of vehicles for site operatives and visitors; ii) Loading and unloading of plant and materials; iii) Storage of plant and materials used in constructing the development; iv) The erection and maintenance of security hoarding including decorative displays; v) Wheel washing facilities; vi) Measures to control the emission of noise dust and vibration during the construction period. vii) A scheme for recycling/disposing of waste resulting from demolition and construction works. REASON: In the interest of neighbour amenity and highways safety and in accordance with policy SD4 of the Redcar and Cleveland Local Plan. |
| 8 | Prior to the commencement of any phase of development plans showing the existing and proposed ground levels over the site together with finished floor levels and maximum building heights shall be submitted to and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure a satisfactory relationship between existing and proposed buildings in accordance with policy SD4 of the Local Plan. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as construction activity and site preparation can change existing levels resulting in increased ground levels which the authority needs to consider. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Councillor C Cawley (DORMANSTOWN) | 11/10/2023 | - |
| Councillor D Powlay (DORMANSTOWN) | 11/10/2023 | - |
| Engineering Team (Highways) | 11/10/2023 | - |
| Engineers (Local Lead Flood Authority) | 11/10/2023 | - |
| Environmental Protection Team | 11/10/2023 | - |
| Northumbrian Water Ltd | 11/10/2023 | - |