Location
LAND NORTH OF HIGH FARM COTTAGE AND HIGH FARM BUNGALOW AND EAST OF LACKENBY SUBSTATION
LACKENBY LANE
LACKENBY
Proposal
DISCHARGE OF CONDITION 6 (HIGHWAY ACCESSES) OF PLANNING PERMISSION R/2020/0832/FF (THE DOGGER BANK PROJECT#3 PERMISSION) FOR STAGE TCPA6(A) FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND FARMS...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGER BANK OFFSHORE WIND FARM PROJECT 3 PROJCO LI
Applicant's Address
SOPHIE DICKSON
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG 3JH
Agent
ROYAL HASKONING D H V
Agent's Address
CLAIRE DAVIES
ROYAL HASKONING D H V
53 PORTLAND STREET
MANCHESTER
M1 3LF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
30/03/2023
Date Valid
30/03/2023
Expiry
25/05/2023
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
24/04/2023
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (1) No stage may commence until, for that stage, written details identifying the routes and accesses for operational maintenance have, following consultation with the highway authority, been submitted to and approved by the local planning authority. (2) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this condition may cover one or more stages. REASON: In the interest of highway safety and maintenance to ensure the development complies with policy SD4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The provision of new access points will be required in advance of development commencing where new access points are required. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 294 kb | 30/03/2023 | |
| Consultee Responses | |||
| Consultee response - Engineering Team (Highways) | 47 kb | 03/04/2023 | |
| Decision | |||
| Compliance Decision Notice | 257 kb | 24/04/2023 | |
| Officer Report | |||
| Compliance Officer Report | 154 kb | 24/04/2023 | |
| Supporting Documentation | |||
| Highways and Access Management Plan | 479 kb | 30/03/2023 | |
| Cover Letter | 143 kb | 30/03/2023 | |
| Highways and Access Management Plan Appendix 2.1 | 7502 kb | 30/03/2023 | |
| Highways and Access Management Plan Appendix 2.2 | 3549 kb | 30/03/2023 | |
| Highways and Access Management Plan Appendix 3.1 | 2326 kb | 30/03/2023 | |
| Highways and Access Management Plan Appendix 4.1 | 2579 kb | 30/03/2023 | |
| Highways and Access Management Plan Appendix 4.2 | 3206 kb | 30/03/2023 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 30/03/2023 | - |