Location
DOGGER BANK WIND FARM C
ONSHORE CONVERTER STATION (OCS) AND ASSOCIATED WORKS NEAR LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 24 (HIGHWAYS & ACCESS MANAGMENT PLAN) IN RELATION TO STAGE 3 FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS SP...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGER BANK OFFSHORE WIND FARM PROJECT 3 PROJCO LI
Applicant's Address
MISS SOPHIE DICKSON
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG 3JH
Agent
Royal HaskoningDHV
Agent's Address
CLAIRE DAVIES
ROYAL HASKONINGDHV
9TH FLOOR MANCHESTER ONE
53 PORTLAND STREET
MANCHESTER
M1 3LF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
30/03/2023
Date Valid
30/03/2023
Expiry
25/05/2023
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
24/04/2023
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (1) No stage may commence until, for that stage, written details of the siting, design, layout and any access management measures for any new permanent or temporary means of access to or from a public highway to be used by vehicular traffic, or any alteration to an existing means of access to or from a public highway used by vehicular traffic, have, after consultation with the highway authority, been submitted to and approved by the local planning authority. (2) No stage may commence until, for that stage, written details identifying the routes and accesses for operational maintenance have, following consultation with the highway authority, been submitted to and approved by the local planning authority. (3) All highway accesses must be constructed, maintained and removed in accordance with the approved details. (4) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this condition may cover one or more stages. REASON: In the interest of highway safety and maintenance to ensure the development complies with policy SD4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The provision of new access points will be required in advance of development commencing where new access points are required. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 295 kb | 30/03/2023 | |
| Consultee Responses | |||
| Consultee response - Engineering Team (Highways) | 47 kb | 03/04/2023 | |
| Decision | |||
| Compliance Decision Notice | 260 kb | 24/04/2023 | |
| Officer Report | |||
| Compliance Officer Report | 142 kb | 24/04/2023 | |
| Supporting Documentation | |||
| Highways and Access Management Plan | 479 kb | 30/03/2023 | |
| Cover Letter | 142 kb | 30/03/2023 | |
| Highways and Access Management Plan Appendix 2.1 | 7502 kb | 30/03/2023 | |
| Highways and Access Management Plan Appendix 2.2 | 3549 kb | 30/03/2023 | |
| Highways and Access Management Plan Appendix 3.1 | 2326 kb | 30/03/2023 | |
| Highways and Access Management Plan Appendix 4.1 | 2579 kb | 30/03/2023 | |
| Highways and Access Management Plan Appendix 4.2 | 3206 kb | 30/03/2023 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 30/03/2023 | - |