R/2023/0255/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C OFFSHORE WIND FARM CABLE CORRIDOR, FROM THE DOGGER BANK C ONSHORE CONVERTER STATION SOUTH OF WILTON INTERNATIONAL UP TO LACKENBY NATIONAL GRID SUBSTATION
Proposal
DISCHARGE OF CONDITION 12 (CONSTRUCTION TRAFFIC MANAGMENT PLAN) OF PLANNING PERMISSION R/2020/0355/FFM FOR STAGE TCPA 1 AND TCPA 6 FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE W...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Saltburn, Marske and New Marske CP
Applicant
DOGGER BANK OFFSHORE WIND FARM PROJECT 3 PROJCO LI
Applicant's Address
SOPHIE DICKSON 1 FORBURY PLACE 43 FORBURY ROAD READING RG 3JH
Agent
ROYAL HASKONING D H V
Agent's Address
CLAIRE DAVIES ROYAL HASKONING D H V 53 PORTLAND STREET MANCHESTER M1 3LF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
30/03/2023
Date Valid
30/03/2023
Expiry
25/05/2023
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
19/04/2023
Decision Level
-

Conditions table
# Condition Details
1 (1) No stage may commence until, for that stage, written details of a construction traffic management plan (“CTMP”) and a construction travel plan (“CTP”), to be used for the management of construction traffic for that stage, has been submitted to and approved by the local planning authority following consultation with Highways England. (2) Each CTMP and CTP must include details (including agreed routes) for abnormal indivisible loads (“AILs”) that may be delivered by road (or confirmation that no AILs are required for construction of the authorised development), and the approved details must be adhered to at all times when AILs are transported to or from the authorised development by road. (3) Notices must be erected and maintained throughout the period of construction at construction site exits, in accordance with the CTMP, indicating to drivers the routes agreed by the local planning authority for traffic entering and leaving sites. (4) For the avoidance of doubt, each scheme approved under paragraph (1) of this condition may cover one or more stages. REASON: In the interest of highways safety in accordance with policy SD4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as it relates to construction details which are often the first works on site and relate to site preparation.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 296 kb 30/03/2023
Consultee Responses
Consultee response - Engineering Team (Highways) 46 kb 03/04/2023
Decision
Compliance Decision Notice 242 kb 19/04/2023
Officer Report
Compliance Officer Report 165 kb 19/04/2023
Supporting Documentation
Construction Traffic Management Plan 357 kb 30/03/2023
Construction Traffic Management Plan Appendix 1.1 2336 kb 30/03/2023
Construction Traffic Management Plan Appendix 2.1 7510 kb 30/03/2023
Construction Traffic Management Plan Appendix 2.2 3557 kb 30/03/2023
Construction Traffic Management Plan Appendix 3.1 2588 kb 30/03/2023
Construction Traffic Management Plan Appendix 3.2 2566 kb 30/03/2023
Construction Traffic Management Plan Appendix 3.3 1867 kb 30/03/2023
Construction Travel Plan 392 kb 30/03/2023
Construction Travel Plan Appendix 2.1 7500 kb 30/03/2023
Construction Travel Plan Appendix 2.2 3546 kb 30/03/2023
Construction Travel Plan Appendix 4.1 2326 kb 30/03/2023
Construction Travel Plan Appendix 4.2 1330 kb 30/03/2023
Construction Travel Plan Appendix 4.3 1532 kb 30/03/2023
Construction Travel Plan Appendix 4.4 1619 kb 30/03/2023
Cover Letter 144 kb 30/03/2023