R/2023/0235/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C OFFSHORE WIND FARM CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 25 (SURFACE AND FOUL WATER DRAINAGE) IN RELATION TO STAGE 3 FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS SPE...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGER BANK OFFSHORE WIND FARM PROJECT 3 PROJCO LI
Applicant's Address
MISS SOPHIE DICKSON 1 FORBURY PLACE 43 FORBURY ROAD READING RG 3JH
Agent
Royal HaskoningDHV
Agent's Address
CLAIRE DAVIES ROYAL HASKONINGDHV 9TH FLOOR MANCHESTER ONE 53 PORTLAND STREET MANCHESTER M1 3LF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
27/03/2023
Date Valid
27/03/2023
Expiry
22/05/2023
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
04/05/2023
Decision Level
-

Conditions table
# Condition Details
1 Requirement 25 (1) No stage of the onshore works may commence until written details of the surface and (if any) foul water drainage system (including means of pollution control) for that stage have, following consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the relevant planning authority. (2) The surface water drainage system works must restrict surface water discharge to no more than the greenfield run-off rate (16.2 litres per second) in line with the recommendations of the flood risk assessment (Appendix B to Chapter 24 of the environmental statement). (3) The submitted details must for each stage— (a) provide information about the design storm period and intensity, the method employed to delay and control the surface water discharged from the site (surface water drainage scheme); (b) include a timetable for implementation (foul and surface water schemes); and (c) provide a management and maintenance plan for the lifetime of the proposed schemes (foul and surface water management) (4) The surface and foul water drainage systems must be constructed, managed and maintained in accordance with the approved details. (5) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this requirement may cover one or more stages of the onshore works.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 295 kb 27/03/2023
Consultee Responses
Consultee response - Environment Agency 30 kb 12/04/2023
Consultee response - Engineers (Local Lead Flood Authority) 448 kb 27/04/2023
Decision
Compliance Decision Notice 260 kb 04/05/2023
Officer Report
Compliance Officer Report 159 kb 04/05/2023
Supporting Documentation
Requirement 25 - Drainage DCO Stage 3 681 kb 27/03/2023
Requirement 25 - Drainage Scheme Stage 3 Appendix 2.1 7316 kb 27/03/2023
Requirement 25 - Drainage Scheme Stage 3 Appendix 2.2 3362 kb 27/03/2023
Requirement 25 - Covering Letter R25 Drainage Stage 3 141 kb 27/03/2023
Consultee Name Date Letter Sent Consultation Expiry Date
Engineers (Local Lead Flood Authority) 27/03/2023 -
Environment Agency 27/03/2023 -
Northumbrian Water Ltd 27/03/2023 -