Location
LAND ALONG THE DOGGER BANK C OFFSHORE WIND FARM CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 23 (FENCING AND OTHER MEANS OF ENCLOSURE FOR ONSHORE WORKS) FOR STAGE 3 OF TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOP...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGER BANK OFFSHORE WIND FARM PROJECT 3 PROJCO LI
Applicant's Address
MISS SOPHIE DICKSON
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG 3JH
Agent
Royal HaskoningDHV
Agent's Address
CLAIRE DAVIES
ROYAL HASKONINGDHV
9TH FLOOR MANCHESTER ONE
53 PORTLAND STREET
MANCHESTER
M1 3LF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
27/03/2023
Date Valid
27/03/2023
Expiry
22/05/2023
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
18/04/2023
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (1) No stage of the onshore works may commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure for that stage have been submitted to and approved by the relevant planning authority. (2) All construction sites must remain securely fenced at all times during construction of the onshore works. (3) Any temporary fencing must be removed on completion of the relevant work. (4) Any approved permanent fencing in relation to the Project A converter station works must be completed before any part or parts of the relevant work is brought into use. (a) Any approved permanent fencing in relation to the Project B converter station works must be completed before any part or parts of the relevant work is brought into use. (5) Fencing, walls and other means of enclosure must be provided in accordance with the approved details. (6) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this requirement may cover one or more stages of the onshore works. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 295 kb | 27/03/2023 | |
| Consultee Responses | |||
| Consultee response - Engineering Team (Highways) | 47 kb | 03/04/2023 | |
| Decision | |||
| Decision Notice | 457 kb | 18/04/2023 | |
| Officer Report | |||
| Officer Report | 314 kb | 18/04/2023 | |
| Supporting Documentation | |||
| Requirement 23 - Fencing Proposals DCO Stage 3 | 249 kb | 27/03/2023 | |
| Requirement 23 - Fencing Proposals DCO Stage 3 Appendix A.1 | 7309 kb | 27/03/2023 | |
| Requirement 23 - Fencing Proposals Dco Stage 3 Appendix A.2 | 3358 kb | 27/03/2023 | |
| Requirement 23 - Fencing Proposals Dco Stage 3 Appendix B | 1603 kb | 27/03/2023 | |
| Covering Letter R23 - Fencing Stage 3 | 141 kb | 27/03/2023 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 27/03/2023 | - |