Location
LAND AT THE LANDFALL OF THE DOGGER BANK C OFFSHORE WIND FARM
NEAR MARSKE BY THE SEA
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 32 (CONSTRUCTION TRAFFIC MANAGEMENT PLAN AND CONSTRUCTION TRAVEL PLAN) FOR STAGE 1 (PROJECT A) FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION O...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGER BANK OFFSHORE WIND FARM PROJECT 3 PROJCO LI
Applicant's Address
MISS SOPHIE DICKSON
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG 3JH
Agent
CLAIRE DAVIES
Agent's Address
ROYAL HASKONINGDHV
9TH FLOOR MANCHESTER ONE
53 PORTLAND STREET
MANCHESTER
M1 3LF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
29/11/2022
Date Valid
29/11/2022
Expiry
24/01/2023
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
11/01/2023
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (1) No stage of the onshore works may commence until for that stage, written details of a construction traffic management plan (“CTMP”) and a construction travel plan (“CTP”), to be used for the management of construction traffic for that stage, has been submitted to and approved by the relevant planning authority and Highways England. (2) Each CTMP and CTP must include details (including agreed routes) for abnormal indivisible loads (“AILs”) that may be delivered by road (or confirmation that no AILs are required for construction of the authorised development), and the approved details must be adhered to at all times when AILs are transported to or from the authorised development by road (3) Notices must be erected and maintained throughout the period of construction at construction site exits, in accordance with the CTMP, indicating to drivers the routes agreed by the relevant planning authority for traffic entering and leaving sites. (4) For the avoidance of doubt, each scheme approved under paragraph (1) of this requirement may cover one or more stages of the onshore works. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 220 kb | 29/11/2022 | |
| Covering Letter Requirement 32 CTMP And CTP Stage 1 | 383 kb | 29/11/2022 | |
| Consultee Responses | |||
| Consultee response - Engineering Team (Highways) | 452 kb | 10/01/2023 | |
| Decision | |||
| Compliance Decision Notice | 454 kb | 11/01/2023 | |
| Officer Report | |||
| Compliance Officer Report | 379 kb | 11/01/2023 | |
| Supporting Documentation | |||
| Construction Traffic Management Plan DCO Stage 1 | 5793 kb | 29/11/2022 | |
| Construction Travel Plan DCO Stage 1 | 4080 kb | 29/11/2022 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 29/11/2022 | - |