R/2022/0945/CD

Planning Application Details - Official Consultation has expired.

Location
LAND AT THE LANDFALL OF THE DOGGER BANK C OFFSHORE WIND FARM NEAR MARSKE BY THE SEA
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 25 (SURFACE AND FOUL WATER DRAINAGE) IN RELATION TO STAGE 1 OF THE ONSHORE WORK FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISE...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGER BANK OFFSHORE WIND FARM PROJECT 3 PROJCO LI
Applicant's Address
MISS SOPHIE DICKSON 1 FORBURY PLACE 43 FORBURY ROAD READING RG 3JH
Agent
Royal HaskoningDHV
Agent's Address
CLAIRE DAVIES ROYAL HASKONINGDHV 9TH FLOOR MANCHESTER ONE 53 PORTLAND STREET MANCHESTER M1 3LF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
25/11/2022
Date Valid
25/11/2022
Expiry
20/01/2023
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
05/01/2023
Decision Level
-

Conditions table
# Condition Details
1 Requirement 25 (1) No stage of the onshore works may commence until written details of the surface and (if any) foul water drainage system (including means of pollution control) for that stage have, following consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the relevant planning authority. (2) The surface water drainage system works must restrict surface water discharge to no more than the greenfield run-off rate (16.2 litres per second) in line with the recommendations of the flood risk assessment (Appendix B to Chapter 24 of the environmental statement). (3) The submitted details must for each stage— (a) provide information about the design storm period and intensity, the method employed to delay and control the surface water discharged from the site (surface water drainage scheme); (b) include a timetable for implementation (foul and surface water schemes); and (c) provide a management and maintenance plan for the lifetime of the proposed schemes (foul and surface water management) (4) The surface and foul water drainage systems must be constructed, managed and maintained in accordance with the approved details. (5) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this requirement may cover one or more stages of the onshore works.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 220 kb 25/11/2022
Consultee Responses
Consultee response - Northumbrian Water 74 kb 28/11/2022
Consultee response - Engineers (Local Lead Flood Authority) 451 kb 30/11/2022
Consultee response - Environment Agency 30 kb 16/12/2022
Decision
Compliance Decision Notice 274 kb 05/01/2023
Officer Report
Compliance Officer Report 172 kb 05/01/2023
Supporting Documentation
Cover Letter Requirement 25 Drainage Stage 1 228 kb 25/11/2022
Requirement 25 - Surface and Foul Water Drainage Scheme 3195 kb 25/11/2022
Consultee Name Date Letter Sent Consultation Expiry Date
Engineers (Local Lead Flood Authority) 25/11/2022 -
Environment Agency 25/11/2022 -
Northumbrian Water Ltd 25/11/2022 -