R/2022/0923/CD

Planning Application Details - Official Consultation has expired.

Location
DOGGER BANK WIND FARM C ONSHORE CONVERTER STATION (OCS) AND ASSOCIATED WORKS NEAR LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 28 (CEMP) IN RELATION TO STAGE 1 FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS SPECIFIED IN PART 1 OF SCHEDUL...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGER BANK OFFSHORE WIND FARM PROJECT 3 PROJCO LI
Applicant's Address
MISS SOPHIE DICKSON 1 FORBURY PLACE 43 FORBURY ROAD READING RG 3JH
Agent
CLAIRE DAVIES
Agent's Address
CLAIRE DAVIES ROYAL HASKONINGDHV 9TH FLOOR MANCHESTER ONE 53 PORTLAND STREET MANCHESTER M1 3LF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
17/11/2022
Date Valid
17/11/2022
Expiry
12/01/2023
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
09/01/2023
Decision Level
-

Conditions table
# Condition Details
1 Requirement 28 (1) Before the commencement of each stage, a construction environmental management plan (“CEMP”) for that stage, drafted in accordance with the principles set out in the CoCP, must be submitted to and approved by the local planning authority. (2) All remediation, construction and commissioning works must be undertaken in accordance with each relevant CoCP and CEMP. (3) For the avoidance of doubt, each CEMP approved under paragraph 1 of this condition may cover one or more stages. REASON: In the interest of neighbour amenity, highways safety and protection of ecology value in accordance with policies SD4 and N4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as it relates to construction details which are often the first works on site and relate to site preparation.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 220 kb 17/11/2022
Consultee Responses
Consultee response - Public Rights of Way 450 kb 17/11/2022
Consultee response - Northumbrian Water 740 kb 21/11/2022
Consultee response - Environmental Protection (Contaminated Land) 241 kb 29/11/2022
Consultee response - Environmental Protection (Nuisance) 241 kb 29/11/2022
Consultee response - Natural England 725 kb 09/12/2022
Decision
Decision Notice 455 kb 09/01/2023
Officer Report
Officer Report 364 kb 09/01/2023
Supporting Documentation
Requirement 28 - CEMP DCO Stage 1 4925 kb 17/11/2022
Covering Letter 200 kb 17/11/2022
Consultee Name Date Letter Sent Consultation Expiry Date
Engineering Team (Highways) 17/11/2022 -
Environmental Protection Team 17/11/2022 -
Environmental Protection Team 17/11/2022 -
Natural England 17/11/2022 -
Northumbrian Water Ltd 17/11/2022 -
Public Rights of Way 17/11/2022 -