Location
LAND NORTH OF HIGH FARM COTTAGE AND HIGH FARM BUNGALOW AND EAST OF LACKENBY SUBSTATION LACKENBY LANE LACKENBY
Proposal
DISCHARGE OF CONDITION 7 (DRAINAGE) OF PLANNING PERMISSION R/2020/0832/FF (THE DOGGER BANK PROJECT#3 PERMISSION) FOR STAGE TCPA6(A) (PROJECT A) FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND F...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGER BANK OFFSHORE WIND FARM PROJECT 3 PROJCO LI
Applicant's Address
SOPHIE DICKSON
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG 3JH
Agent
ROYAL HASKONING D H V
Agent's Address
CLAIRE DAVIES
53 PORTLAND STREET
MANCHESTER
M1 3LF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
08/11/2022
Date Valid
08/11/2022
Expiry
03/01/2023
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
16/12/2022
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (1) No stage may commence until written details of the surface and (if any) foul water drainage system (including means of pollution control) for that stage have, following consultation with the relevant sewerage and drainage authorities, been submitted to and approved by the local planning authority. (2) The surface and foul water drainage systems must be constructed, managed and maintained in accordance with the approved details. (3) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this condition may cover one or more stages. REASON: To ensure the development is supported by a suitably designed surface/foul water disposal infrastructure scheme and to minimise the risk flooding in the locality. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as it relates to drainage details which are often the first works on site and relate to site preparation. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 221 kb | 08/11/2022 | |
| Consultee Responses | |||
| Consultee response - Engineers (Local Lead Flood Authority) | 449 kb | 22/11/2022 | |
| Decision | |||
| Compliance Decision Notice | 241 kb | 16/12/2022 | |
| Officer Report | |||
| Compliance Officer Report | 141 kb | 16/12/2022 | |
| Supporting Documentation | |||
| Covering Letter | 143 kb | 08/11/2022 | |
| Condition 7 - Drainage Scheme DCO Stage 12 | 603 kb | 08/11/2022 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineers (Local Lead Flood Authority) | 09/11/2022 | - |