Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR FROM THE SOFIA ONSHORE CONVERTER STATION SOUTH OF WILTON INTERNATIONAL INCLUDING THE CABLE CORRIDOR AND UP TO LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 20 (DETAILED DESIGN), 21 (LANDSCAPING SCHEME), 23 (FENCING PLAN), 24 (HIGHWAYS ACCESS MANAGEMENT PLAN (HAMP)), 25 (SURFACE AND FOUL WATER DRAINAGE SCHEME) AND 32 (CONSTRUCTION TRAFFIC MANAGMENT PLAN) STAGE 5 PART 3 FOR TWO OFFSHORE WIND TURBINE GENERATING STATIO...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
PROJCO 3 & SOWFL LIMITED
Applicant's Address
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG1 3JH
Agent
Arcus Consultancy Services Ltd
Agent's Address
MEGAN BARRIE
SUITE 1C
SWINEGATE COURT EAST
3 SWINEGATE
YORK
YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
18/10/2022
Date Valid
18/10/2022
Expiry
13/12/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
09/12/2022
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | Requirement 20 (1) Except where a stage of the onshore works (or part thereof) is/are carried out in accordance with the plans referred to in Requirement 19, no stage of the onshore works may commence until details of the layout, scale, levels and external appearance (in so far as those details are not shown on those plans) for the relevant stage have been submitted to and approved by the relevant planning authority. Where the relevant stage includes all or any part of Work Nos. 4A, 5A, 4B or 5B, this must include a section showing cable depths for Work Nos. 4A, 5A, 4B or 5B as appropriate (2) No building forming part of Work No. 7 may exceed 20 metres in height above the floor level for that location, excluding lightning protection. (3) For the avoidance of doubt (and to the extent that such works are not carried out in accordance with the plans referred to in Requirement 19 and therefore require approval)— (a) in relation to Work No. 7, the relevant planning authority may approve— (i) the detailed design for the Project A converter station works and the Project B converter station works as separate stages (or part thereof); and (ii) the detailed design for the Project A converter station enabling works and the Project B converter station enabling works as either separate stages (or part thereof) or as a single stage (or part thereof) comprising the Work No.7 enabling works; (b) in relation to Work No. 8S, the relevant planning authority may approve the detailed design for the Project A HVAC cable works and the Project B HVAC cable works as either separate stages (or part thereof) or the same stage (or part thereof); (c) in relation to Work No. 9, the relevant planning authority may approve the detailed design for the Project A National Grid substation connection works and the Project B National Grid substation connection works as either separate stages (or part thereof) or the same stage (or part thereof); (d) in relation to Work Nos. 2A, 2B, 3A, 3B, 4A, 4B, 5A, 5B, 6A, 6B, 8A, 8B and 8S the relevant planning authority may approve the detailed design of the cable preparation works as a separate stage (or part thereof); and (4) The details approved under paragraph (1) may cover one or more stages of the onshore works.” |
| 2 | Requirement 21 (1) No stage of the onshore works may commence until a written landscaping scheme and associated work programme for that stage has been submitted to, and approved by, the relevant planning authority. Each landscaping scheme must include details of all proposed hard and soft landscaping works for the relevant stage, including— (a) location, number, species, size and planning density of any proposed planting, including any trees; (b) cultivation, importing of materials and other operations to ensure plant establishment; (c) proposed finished ground levels; (d) minor structures, such as furniture, refuse or other storage units, signs and lighting; (e) proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports; (f) details of existing trees to be retained, with measures for their protection during the construction period; (g) retained historic landscape features and proposals for restoration, where relevant; and (h) implementation timetables for all landscaping works. (2) For the avoidance of doubt, each landscaping scheme approved under paragraph (1) of this requirement may cover one or more stages of the onshore works. |
| 3 | Requirement 23 (1) No stage of the onshore works may commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure for that stage have been submitted to and approved by the relevant planning authority. (2) All construction sites must remain securely fenced at all times during construction of the onshore works. (3) Any temporary fencing must be removed on completion of the relevant work. (4) Any approved permanent fencing in relation to the Project A converter station works must be completed before any part or parts of the relevant work is brought into use. (a) Any approved permanent fencing in relation to the Project B converter station works must be completed before any part or parts of the relevant work is brought into use. (5) Fencing, walls and other means of enclosure must be provided in accordance with the approved details. (6) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this requirement may cover one or more stages of the onshore works. |
| 4 | Requirement 24 - Highways accesses (1) No stage of the onshore works may commence until, for that stage, written details of the siting, design, layout and any access management measures for any new permanent or temporary means of access to or from a public highway to be used by vehicular traffic, or any alteration to an existing means of access to or from a public highway used by vehicular traffic, has, after consultation with the highway authority, been submitted to and approved by the relevant planning authority. (2) No stage of the onshore works may commence until, for that stage, written details identifying the routes and accesses for operational maintenance has, following consultation with the highway authority, been submitted to and approved by the relevant planning authority. (3) All highway accesses must be constructed, maintained and removed in accordance with the approved details. |
| 5 | Requirement 25 - Surface and Foul Water Drainage (1) No stage of the onshore works may commence until written details of the surface and (if any) foul water drainage system (including means of pollution control) for that stage have, following consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the relevant planning authority. (2) The surface water drainage system works must restrict surface water discharge to no more than the greenfield run-off rate (1.62 litres per second) in line with the recommendations of the flood risk assessment (Appendix B to Chapter 24 of the environmental statement). (3) The submitted details must— (a) provide information about the design storm period and intensity, the method employed to delay and control the surface water discharged from the site (surface water drainage scheme); (b) include a timetable for implementation (foul and surface water schemes); and (c) provide a management and maintenance plan for the lifetime of the proposed schemes (foul and surface water management) |
| 6 | Requirement 32 (1) No stage of the onshore works may commence until for that stage, written details of a construction traffic management plan (“CTMP”) and a construction travel plan (“CTP”), to be used for the management of construction traffic for that stage, has been submitted to and approved by the relevant planning authority and Highways England. (2) Each CTMP and CTP must include details (including agreed routes) for abnormal indivisible loads (“AILs”) that may be delivered by road (or confirmation that no AILs are required for construction of the authorised development), and the approved details must be adhered to at all times when AILs are transported to or from the authorised development by road (3) Notices must be erected and maintained throughout the period of construction at construction site exits, in accordance with the CTMP, indicating to drivers the routes agreed by the relevant planning authority for traffic entering and leaving sites. (4) For the avoidance of doubt, each scheme approved under paragraph (1) of this requirement may cover one or more stages of the onshore works. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 19/10/2022 | - |
| Engineers (Local Lead Flood Authority) | 19/10/2022 | - |
| Environment Agency | 19/10/2022 | - |
| Northumbrian Water Ltd | 19/10/2022 | - |
| Public Rights of Way | 19/10/2022 | - |