Location
LAND NORTH OF TEESWORKS AREA AND NORTH EAST OF
STEEL HOUSE
TRUNK ROAD
REDCAR
Proposal
DISCHARGE OF CONDITION 3 (CEMP) ON PLANNING APPROVAL R/2022/0494/FFM FOR ENGINEERING OPERATIONS ASSOCIATED WITH THE REMOVAL OF MOUNDS, INSTALLATION OF HAUL ROAD; TEMPORARY BRIDGE OVER WATERCOURSE AND ASSOCIATED WORKS
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
LICHFIELDS
Applicant's Address
C/O AGENT
ST NICHOLAS BUILDING
ST NICHOLAS STREET
C/O AGENT
NE1 1RF
Agent
Lichfields
Agent's Address
MR ADRIAN ARMSTRONG
ST NICHOLAS BUILDING
ST NICHOLAS STREET
NEWCASTLE UPON TYNE
NE1 1RF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
27/09/2022
Date Valid
27/09/2022
Expiry
22/11/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
08/11/2022
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | No development shall take place until a Construction Environmental Management Plan (CEMP) for that phase of the development has been submitted to and approved in writing by the Local Planning Authority. The approved CEMP shall be adhered to throughout the construction period of that phase. The CEMP shall include details of any phasing of the approved works across the site and shall demonstrate how the mitigation measures set out in the Ecological Impact Assessment, INCA,, dated 26 February 2021 have been incorporated in the construction methods. The CEMP shall also include the following details: i Sediment Management Plan ii Biosecurity Plan iii Pollution Prevention Plan iv Dust Management Plan v Measures to control the deposit of mud and debris on adjoining public highways vi Site fencing and security vii Measures to control surface water and other water generated as part of the works REASON: In the interest of neighbour amenity, highways safety and protection of sites of ecological value in accordance with policies SD4 and N4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as it relates to construction details which are often the first works on site and relate to site preparation. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 217 kb | 27/09/2022 | |
| Consultee Responses | |||
| Consultee response - Natural England | 725 kb | 06/10/2022 | |
| Consultee response - Environmental Protection (Nuisance) | 14 kb | 07/10/2022 | |
| Consultee response - Engineers (Local Lead Flood Authority) | 448 kb | 12/10/2022 | |
| Consultee response - Engineering Team (Highways) | 686 kb | 17/10/2022 | |
| Decision | |||
| Compliance Decision Notice | 454 kb | 08/11/2022 | |
| Officer Report | |||
| Compliance Officer Report | 365 kb | 08/11/2022 | |
| Supporting Documentation | |||
| Covering Letter | 208 kb | 27/09/2022 | |
| Condition 3 - Construction Environmental Management Plan (CEMP) | 620 kb | 27/09/2022 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Councillor S Jeffrey (SOUTH BANK) | 27/09/2022 | - |
| Councillor Sandra Smith (SOUTH BANK) | 27/09/2022 | - |
| Engineering Team (Highways) | 27/09/2022 | - |
| Engineers (Local Lead Flood Authority) | 27/09/2022 | - |
| Environment Agency | 27/09/2022 | - |
| Environmental Protection Team | 27/09/2022 | - |
| Natural England | 27/09/2022 | - |