R/2022/0385/FF

Planning Application Details - Official Consultation has expired.

Location
REDCAR RACECOURSE THRUSH ROAD REDCAR TS10 2BY
Proposal
CREATION OF NEW 50 SPACE HORSEBOX CAR PARK INCLUDING NEW VEHICULAR AND PEDESTRIAN ACCESSES OFF WEST DYKE ROAD, 2.5M HIGH BOUNDARY WALL AND ASSOCIATED WORKS
Application Type
Full
Status
Approved
Parish(es)
Applicant
REDCAR RACING LIMITED
Applicant's Address
C/O AGENT
Agent
Rapleys LLP
Agent's Address
MR MARCIN KOSZYCZAREK RAPLEYS LLP YORK HOUSE YORK STREET MANCHESTER M2 3BB
Agent's work phone
Agent's email
Case Officer
Mrs C Griffiths
Case Officer Telephone
01287 612629
Case Officer Email
claire.griffiths@redcar-cleveland.gov.uk
Consultation Start
05/05/2022
Weekly List Expiry Date
-
Date Received
22/04/2022
Date Valid
04/05/2022
Expiry
29/07/2022
Consultation Expiry
05/06/2022
associated_bldreg
-
Decision
GRANT PLANNING PERMISSION
Decision Date
29/07/2022
Decision Level
-

Conditions table
# Condition Details
1 The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2 The development hereby permitted shall be carried out in accordance with the following approved plans: Location plan received by the Local Planning Authority on 04/05/2022 Site plan as proposed received by the Local Planning Authority on 04/05/2022 Entrance, gates and boundary treatments received by the Local Planning Authority on 04/05/2022 REASON: To accord with the terms of the planning application.
3 Prior to the commencement of the development, or in such extended time as may be agreed in writing with the Local Planning Authority, details shall be submitted and approved of the surface water drainage scheme and the development shall be completed in accordance with the approved scheme. The design of the drainage scheme shall include; (i) Restriction of surface water greenfield run-off rates (QBAR value) with sufficient storage within the system to accommodate a 1 in 30 year storm. (ii)The method used for calculation of the existing greenfield run-off rate shall be the ICP SUDS method. The design shall also ensure that storm water resulting from a 1 in 100 year event, plus climate change surcharging the system, can be stored on site with minimal risk to persons or property and without overflowing into drains, local highways or watercourses. (iii) Full Micro Drainage design files (mdx files) including a catchment plan (iv) The flow path of flood waters for the site as a result on a 1 in 100 year event plus climate change REASON: To ensure the development is supported by a suitably designed surface water disposal infrastructure scheme and to minimise the risk flooding in the locality. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation.
4 Prior to the commencement of the development, or in such extended time that may be agreed with the Local Planning Authority, details of a Surface Water Drainage Management Plan shall be submitted and approved by the Local Planning Authority. The Management Plan shall include; (i) The timetable and phasing for construction of the drainage system (ii) Details of any control structure(s) (iii) Details of surface water storage structures (iv) Measures to control silt levels entering the system and out falling into any watercourse during the construction process The development shall, in all respects, be carried out in accordance with the approved Management Plan. REASON: To ensure the development is supported by an appropriately designed surface water disposal infrastructure scheme and to minimise the risk of increased flooding and contamination of the system during the construction process. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation.
5 The development shall not be occupied until a Management & Maintenance Plan for the surface water drainage scheme has been submitted to and approved by the Local planning Authority; the plan shall include details of the following; (i) A plan clearly identifying the sections of surface water system that are to be adopted (ii) Arrangements for the short and long term maintenance of the SuDS elements of the surface water system REASON: To ensure that the surface water drainage infrastructure is maintained to minimise the risk flooding in the locality.
6 Statement of Co-operative Working: The Local Planning Authority considers that the application as originally submitted is a satisfactory scheme and therefore no negotiations have been necessary.
7 Informative Note: The application site is on/close to land that has been identified as having a history of potential contamination. It is not considered that the development proposed will give rise to 'significant risk' to health or pollution of controlled waters. It is recommended, however, that the attention of the applicant be drawn to the risk of contaminants in, on or under the site.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 270 kb 22/04/2022
Covering Letter 492 kb 22/04/2022
Consultee Responses
Consultee response - Environmental Protection (Nuisance) 242 kb 06/05/2022
Consultee response - Environmental Protection (Contaminated Land) 193 kb 17/05/2022
Consultee response - Engineers (Local Lead Flood Authority) 453 kb 18/05/2022
Consultee response - Engineering Team (Highways) 629 kb 29/06/2022
Consultee response - Engineering Team (Highways) (2) 52 kb 29/07/2022
Decision
Decision Notice 424 kb 29/07/2022
Location Plan
Location Plan 304 kb 04/05/2022
Officer Report
Officer Report 419 kb 29/07/2022
Representations
Neighbour Comments - Wheeldon C 452 kb 06/05/2022
Neighbour Comments - Bowers N 248 kb 16/05/2022
Plans
Site Plan as Proposed 399 kb 04/05/2022
Site Plan as Existing 295 kb 04/05/2022
Entrance; Gate; Signage and Boundary Walling Plan 1062 kb 04/05/2022
Supporting Documentation
Transport Statement 3132 kb 22/04/2022
Horsebox Parking Lighting Assessment 2306 kb 22/04/2022
Consultee Name Date Letter Sent Consultation Expiry Date
Councillor C Jones (WEST DYKE) 05/05/2022 -
Councillor M Head (WEST DYKE) 05/05/2022 -
Councillor M Ovens (WEST DYKE) 05/05/2022 -
Engineering Team (Highways) 05/05/2022 -
Engineering Team (Highways) 05/05/2022 -
Engineers (Local Lead Flood Authority) 05/05/2022 -
Environmental Protection Team 05/05/2022 -
Environmental Protection Team 05/05/2022 -
Health & Safety-Food (Food Team) 05/05/2022 -
Address Date Sent Date Reconsulted Expiry Date
68 West Dyke Road - - -
86-88Westdyke road Redcar - - -
68 WEST DYKE ROAD REDCAR TS10 1HL 05/05/2022 - 26/05/2022
70 WEST DYKE ROAD REDCAR TS10 1HL 05/05/2022 - 26/05/2022
FLAT 5 2 EASSON ROAD REDCAR TS10 1HJ 05/05/2022 - 26/05/2022
FLAT 6 2 EASSON ROAD REDCAR TS10 1HJ 05/05/2022 - 26/05/2022
FLAT 1 2 EASSON ROAD REDCAR TS10 1HJ 05/05/2022 - 26/05/2022
FLAT 2 2 EASSON ROAD REDCAR TS10 1HJ 05/05/2022 - 26/05/2022
FLAT 3 2 EASSON ROAD REDCAR TS10 1HJ 05/05/2022 - 26/05/2022
FLAT 4 2 EASSON ROAD REDCAR TS10 1HJ 05/05/2022 - 26/05/2022
24 STABLE MEWS REDCAR TS10 2HL 05/05/2022 - 26/05/2022
GROUNDSMANS HOUSE RACECOURSE HOUSE THRUSH ROAD REDCAR TS10 2BY 05/05/2022 - 26/05/2022
Site or Press Description Display Date Expiry Date
S SITE NOTICE ONLY 13/05/2022 05/06/2022