R/2022/0324/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
RESUBMISSION OF DETAILS FOR REQUIREMENT 32 (CONSTRUCTION TRAFFIC ROUTING & MANAGEMENT PLANS) FOR STAGE 5 PART 2 FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVE...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIM
Applicant's Address
- - 1 FORBURY PLACE 43 FORBURY ROAD READING RG1 3JH
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER SUITE 1C SWINEGATE COURT EAST 3 SWINEGATE YORK YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
04/04/2022
Date Valid
04/04/2022
Expiry
01/06/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
01/06/2022
Decision Level
-

Conditions table
# Condition Details
1 Requirement 32 (1) No stage of the onshore works may commence until for that stage, written details of a construction traffic management plan (“CTMP”) and a construction travel plan (“CTP”), to be used for the management of construction traffic for that stage, has been submitted to and approved by the relevant planning authority and Highways England. (2) Each CTMP and CTP must include details (including agreed routes) for abnormal indivisible loads (“AILs”) that may be delivered by road (or confirmation that no AILs are required for construction of the authorised development), and the approved details must be adhered to at all times when AILs are transported to or from the authorised development by road (3) Notices must be erected and maintained throughout the period of construction at construction site exits, in accordance with the CTMP, indicating to drivers the routes agreed by the relevant planning authority for traffic entering and leaving sites. (4) For the avoidance of doubt, each scheme approved under paragraph (1) of this requirement may cover one or more stages of the onshore works.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 220 kb 04/04/2022
Covering Letter 197 kb 04/04/2022
Consultee Responses
Consultee response - Engineering Team (Highways) 447 kb 28/04/2022
Decision
Compliance Decision Notice R20220324cd 129 kb 01/06/2022
Supporting Documentation
Requirement 32 - Preliminary Drill Site Arrangement Bs Rev03 Extended Area 305 kb 04/04/2022
Consultee Name Date Letter Sent Consultation Expiry Date
Engineering Team (Highways) 06/04/2022 -