Location
DOGGER BANK WIND FARM C
ONSHORE CONVERTER STATION (OCS) AND ASSOCIATED WORKS NEAR LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 23 (FENCING AND OTHER MEANS OF ENCLOSURE FOR ONSHORE WORKS) IN RELATION TO STAGE 9 FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL
DESCRIPTION OF THE AUTHO...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO 3 L
Applicant's Address
SOPHIE DICKSON
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG1 3JH
Agent
Royal HaskoningDHV
Agent's Address
CLAIRE DAVIES
ROYAL HASKONING D H V
53 PORTLAND STREET
MANCHESTER
M1 3LF
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
24/03/2022
Date Valid
24/03/2022
Expiry
19/05/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
11/05/2022
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | Requirement 23 (1) No stage of the onshore works may commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure for that stage have been submitted to and approved by the relevant planning authority. (2) All construction sites must remain securely fenced at all times during construction of the onshore works. (3) Any temporary fencing must be removed on completion of the relevant work. (4) Any approved permanent fencing in relation to the Project A converter station works must be completed before any part or parts of the relevant work is brought into use. (a) Any approved permanent fencing in relation to the Project B converter station works must be completed before any part or parts of the relevant work is brought into use. (5) Fencing, walls and other means of enclosure must be provided in accordance with the approved details. (6) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this requirement may cover one or more stages of the onshore works. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 220 kb | 24/03/2022 | |
| Consultee Responses | |||
| Consultee response - Engineering Team (Highways) | 447 kb | 19/04/2022 | |
| Decision | |||
| Compliance Decision Notice R20220279cd | 129 kb | 11/05/2022 | |
| Supporting Documentation | |||
| Covering Letter | 263 kb | 24/03/2022 | |
| Requirement 23 - Fencing Proposals Document | 544 kb | 24/03/2022 | |
| Requirement 23 - Appendix A | 1655 kb | 24/03/2022 | |
| Requirement 23 - Appendix B | 6930 kb | 24/03/2022 | |
| Requirement 23 - Appendix C | 8820 kb | 24/03/2022 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Condition Discharge - David Pedlow | 24/03/2022 | - |
| Engineering Team (Highways) | 24/03/2022 | - |