Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR FROM THE SOFIA ONSHORE CONVERTER STATION SOUTH OF WILTON INTERNATIONAL INCLUDING THE CABLE CORRIDOR AND UP TO LACKENBY NATIONAL GRID SUBSTATION
Proposal
DISCHARGE OF CONDITION 5 (FENCING) OF PLANNING PERMISSION R/2020/0355/FFM FOR STAGE TCPA3 PART 3 FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND FARMS AND LACKENBY SUBSTATION ...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Saltburn, Marske and New Marske CP
Applicant
DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIM
Applicant's Address
- -
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG1 3JH
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER
SUITE 1C
SWINEGATE COURT EAST
3 SWINEGATE
YORK
YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
14/02/2022
Date Valid
14/02/2022
Expiry
11/04/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
29/03/2022
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (1) No stage may commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure for that stage have been submitted to and approved by the local planning authority. (2) All construction sites must remain securely fenced at all times during construction of the works. (3) Any temporary fencing must be removed on completion of the relevant work. (4) Fencing, walls and other means of enclosure must be provided in accordance with the approved details. (5) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this condition may cover one or more stages. REASON: To ensure that any boundary treatments/fences would accord with policy SD4 of the Redcar and Cleveland Local Plan by respecting the character of the site and the surroundings and raising no significant adverse impact on neighbouring occupiers or highway safety. REASON FOR PRECOMMENCEMENT: The provision of fencing will be required early in the development stage. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 253 kb | 14/02/2022 | |
| Covering Letter | 663 kb | 14/02/2022 | |
| Consultee Responses | |||
| Consultee response - Engineering Team (Highways) | 449 kb | 23/02/2022 | |
| Decision | |||
| Compliance Decision Notice R20220123cd | 85 kb | 30/03/2022 | |
| Supporting Documentation | |||
| Condition 5 - Fencing Proposals Document | 806 kb | 14/02/2022 | |
| Condition 5 - Fencing Proposals - Consent Boundaries Plan | 1030 kb | 14/02/2022 | |
| Condition 5 - Fencing Proposals - Staging Plan | 5520 kb | 14/02/2022 | |
| Condition 5 - Fencing Proposals - Layout Plan Phase 01 | 4718 kb | 14/02/2022 | |
| R 2020 0355 FFM Decision Notice | 4325 kb | 14/02/2022 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Condition Discharge - David Pedlow | 15/02/2022 | - |