Location
FORMER CLIFFE GARAGE
HIGH STREET
REDCAR
Proposal
DISCHARGE OF CONDITIONS 3, 4, 6 & 7 OF PLANNING APPROVAL R/2021/0333/FFM FOR CONSTRUCTION OF FOUR STOREY BUILDING TO PROVIDE 16 SPECIALIST SUPPORTED HOUSING APARTMENTS AND STAFF FACILITIES; AND TWO STOREY APARTMENT BLOCK WITH 6 SELF-CONTAINED APARTMENTS
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
MERSTEN LTD
Applicant's Address
MR ANDREW MUZZLEWHITE
CARPENTER COURT
1 MAPLE ROAD
BRAMHALL
STOCKPORT
SK7 2DH
Agent
Chadkirk Consulting Ltd
Agent's Address
MRS AMANDA OAKDEN
39 GREEN CROFT
ROMILEY
STOCKPORT
SK6 4LW
Agent's work phone
Agent's email
Case Officer
Mrs H Conti
Case Officer Telephone
01287 612340
Case Officer Email
helen.conti@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
08/02/2022
Date Valid
08/02/2022
Expiry
05/04/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
07/09/2022
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | Prior to the commencement of the development, or in such extended time as may be agreed in writing with the Local Planning Authority, details shall be submitted and approved of the surface water drainage scheme and the development shall be completed in accordance with the approved scheme. The design of the drainage scheme shall include; (i) Restriction of surface water Greenfield run-off rates (QBAR value) with sufficient storage within the system to accommodate a 1 in 30 year storm. (ii)The method used for calculation of the existing greenfield run-off rate shall be the ICP SUDS method. The design shall also ensure that storm water resulting from a 1 in 100 year event, plus climate change (40%) surcharging the system, can be stored on site with minimal risk to persons or property and without overflowing into drains, local highways or watercourses. The flow path of flood waters for the site as a result on a 1 in 100 year event plus climate change REASON: To ensure the development is supported by a suitably designed surface water disposal infrastructure scheme and to minimise the risk flooding in the locality. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 2 | Prior to the commencement of the development, or in such extended time that may be agreed with the Local Planning Authority, details of a Surface Water Drainage Management Plan shall be submitted and approved by the Local Planning Authority. The Management Plan shall include; (i) The timetable and phasing for construction of the drainage system (ii) Details of any control structure(s) 2 (iii) Details of surface water storage structures (iv) Measures to control silt levels entering the system and out falling into any watercourse during the construction process The development shall, in all respects, be carried out in accordance with the approved Management Plan. REASON: To ensure the development is supported by an appropriately designed surface water disposal infrastructure scheme and to minimise the risk of increased flooding and contamination of the system during the construction process. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 3 | Prior to commencement of construction, a Construction Environmental Management Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide the following; i) The parking of vehicles for site operatives and visitors. ii) Loading and unloading of plant and materials; iii) Storage of plant and materials used in constructing the development; iv) The erection and maintenance of security hoarding including decorative displays; v) Wheel washing facilities. vi) Measures to control the emission of noise dust and vibration during the construction period. vii) A scheme for recycling/disposing of waste resulting from demolition and construction works. REASON: To protect the amenity of nearby residents and in the interests of highway safety REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Councillor C W Quartermain (COATHAM) | 08/02/2022 | - |
| Councillor N Baldwin (COATHAM) | 08/02/2022 | - |
| Engineering Team (Highways) | 08/02/2022 | - |
| Engineers (Local Lead Flood Authority) | 08/02/2022 | - |
| Environmental Protection Team | 08/02/2022 | - |
| Environmental Protection Team | 08/02/2022 | - |
| Northumbrian Water Ltd | 08/02/2022 | - |