R/2022/0076/CD

Planning Application Details - Official Consultation has expired.

Location
LAND NORTH OF HIGH FARM COTTAGE AND HIGH FARM BUNGALOW AND EAST OF LACKENBY SUBSTATION LACKENBY LANE LACKENBY
Proposal
DISCHARGE OF CONDITION 7 (FOUL & SURFACE WATER DRAINAGE SCHEME) FOR STAGE TCPA7(A) OF TCPA#3 OF THE APPROVED DEVELOPMENT OF PLANNING PERMISSION R/2020/0832/FF FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
SOFIA OFFSHORE WIND FARM LIMITED
Applicant's Address
MS KIM GAULD CLARK WINDMILL HILL BUSINESS PARK WHITEHILL WAY SWINDON SN5 6PB
Agent
CLARE RUSSELL
Agent's Address
CLARE RUSSELL 20 WESTERN AVENUE MILTON PARK MILTON ABINGDON OX14 4SH
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
02/02/2022
Date Valid
16/02/2022
Expiry
01/06/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
01/06/2022
Decision Level
-

Conditions table
# Condition Details
1 (1) No stage may commence until written details of the surface and (if any) foul water drainage system (including means of pollution control) for that stage have, following consultation with the relevant sewerage and drainage authorities, been submitted to and approved by the local planning authority. (2) The surface and foul water drainage systems must be constructed, managed and maintained in accordance with the approved details. (3) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this condition may cover one or more stages. REASON: To ensure the development is supported by a suitably designed surface/foul water disposal infrastructure scheme and to minimise the risk flooding in the locality. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as it relates to drainage details which are often the first works on site and relate to site preparation.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 255 kb 16/02/2022
Consultee Responses
Consultee response - Northumbrian Water 375 kb 07/03/2022
Consultee response - Engineers (Local Lead Flood Authority) 451 kb 28/03/2022
Decision
Compliance Decision Notice R20220076cd 130 kb 01/06/2022
Officer Report
Compliance Officer Report 125 kb 17/11/2022
Supporting Documentation
Condition 7 - Appendix 1.1 Consent Bounday Plan 1030 kb 02/02/2022
Condition 7 - Appendix 1.2 Staging Plan 5520 kb 02/02/2022
Condition 7 - Appendix 2.1 Greenfield Runoff Rate Calculations 305 kb 02/02/2022
Condition 7 - Foul And Surface Water Drainage Scheme 912 kb 02/02/2022
Condition 7 - Covering Letter 122 kb 02/02/2022
Consultee Name Date Letter Sent Consultation Expiry Date
Councillor A D Brown (DORMANSTOWN) 17/02/2022 -
Councillor C Cawley (DORMANSTOWN) 17/02/2022 -
Councillor C Massey (ESTON) 17/02/2022 -
Councillor D Rees (ESTON) 17/02/2022 -
Councillor G Williams (ESTON) 17/02/2022 -
Engineers (Local Lead Flood Authority) 17/02/2022 -
Environment Agency 17/02/2022 -
National Grid 17/02/2022 -
Northumbrian Water Ltd 17/02/2022 -