Location
LAND NORTH OF HIGH FARM COTTAGE AND HIGH FARM BUNGALOW AND EAST OF LACKENBY SUBSTATION
LACKENBY LANE
LACKENBY
Proposal
DISCHARGE OF CONDITION 6 (HAMP) FOR STAGE TCPA3(A) OF PLANNING PERMISSION R/2020/0832/FF FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND FARMS AND LACKENBY SUBSTATION AND ASSOCIATED TEMPORARY C...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Saltburn, Marske and New Marske CP
Applicant
DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIM
Applicant's Address
- -
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG1 3JH
Agent
MR TIM WHEELER
Agent's Address
MR TIM WHEELER
SUITE 1C
SWINEGATE COURT EAST
3 SWINEGATE
YORK
YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
02/12/2021
Date Valid
02/12/2021
Expiry
27/01/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
25/01/2022
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (1) No stage may commence until, for that stage, written details identifying the routes and accesses for operational maintenance have, following consultation with the highway authority, been submitted to and approved by the local planning authority. (2) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this condition may cover one or more stages. REASON: In the interest of highway safety and maintenance to ensure the development complies with policy SD4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The provision of new access points will be required in advance of development commencing where new access points are required. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Covering Letter | 141 kb | 02/12/2021 | |
| Application Form | 167 kb | 02/12/2021 | |
| Consultee Responses | |||
| Consultee response - Engineering Team (Highways) | 46 kb | 19/01/2022 | |
| Decision | |||
| Compliance Decision Notice R20211036cd | 118 kb | 25/01/2022 | |
| Officer Report | |||
| Officer Report | 102 kb | 21/01/2022 | |
| Supporting Documentation | |||
| Condition 6 - Hamp Appendix 3.1 | 923 kb | 02/12/2021 | |
| Condition 6 - Hamp Appendix 5.1 | 955 kb | 02/12/2021 | |
| Condition 6 - Hamp Appendix 2.1 | 1667 kb | 02/12/2021 | |
| Condition 6 - Hamp Appendix 2.2 | 1565 kb | 02/12/2021 | |
| Condition 6 - Hamp Appendix 4.1 | 1751 kb | 02/12/2021 | |
| Condition 6 - Hamp Appendix 4.2 | 8731 kb | 02/12/2021 | |
| Condition 6 - Highways Access Managment Plan | 365 kb | 08/12/2021 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 09/12/2021 | - |