Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 24 (HIGHWAYS ACCESS MANAGEMENT PLAN) FOR STAGE 5 PART 3 FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS SPECIFI...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIM
Applicant's Address
- -
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG1 3JH
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER
SUITE 1C
SWINEGATE COURT EAST
3 SWINEGATE
YORK
YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
02/12/2021
Date Valid
02/12/2021
Expiry
27/01/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
25/01/2022
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (Highway accesses 24.—(1) No stage of the onshore works may commence until, for that stage, written details of the siting, design, layout and any access management measures for any new permanent or temporary means of access to or from a public highway to be used by vehicular traffic, or any alteration to an existing means of access to or from a public highway used by vehicular traffic, has, after consultation with the highway authority, been submitted to and approved by the relevant planning authority. (2) No stage of the onshore works may commence until, for that stage, written details identifying the routes and accesses for operational maintenance has, following consultation with the highway authority, been submitted to and approved by the relevant planning authority. (3) All highway accesses must be constructed, maintained and removed in accordance with the approved details. (4) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this requirement may cover one or more stages of the onshore works. Approved Plans/Documents 1.Highways Access Management Plan (Dogger Bank C Reference: RE-PM763-ARCUS-00016 / Sofia Document Reference: 003757616-01) submitted to the Local Planning Authority on 8 December 2020. 2.Appendix 2.1 - Consent Boundaries – OSC Enabling Works - DB-T-DES-0046-02 Rev 03 Offshore Wind Farms – Consent Boundaries: Onshore Converter Station Enabling Works submitted to the Local Planning Authority on 8 December 2020 3.Appendix 2.2 - OCS Enabling Works Stages - DB-T-DES-0040-04 Rev 01 Dogger Bank C & Sofia Onshore Converter Station Enabling Work Stages submitted to the Local Planning Authority on 8 December 2020 4.Appendix 3.1 - Site Access Location Plan - SCP/190608/SK007 Rev B Sofia Offshore Wind Farm TA: Site Access Location Plan submitted to the Local Planning Authority on 8 December 2020 5.Appendix 3.2 - Layout Details and Constructional Specification - 60617518-ACM-XX-00-DR-CE-3005 Rev C Southern Access Road - Proposed Junction with Existing Access Road submitted to the Local Planning Authority on 8 December 2020 6.Appendix 3.3 - Swept Paths - 60617518-ACM-XX-00-DR-CE-3008 - Southern Access Road - Vehicle Tracking submitted to the Local Planning Authority on 8 December 2020 7.Appendix 4.1 - Directional Signing Strategy Masterplan - 190608-D01 Rev B Draft HCV/AIL Traffic Routing and Management Masterplan submitted to the Local Planning Authority on 8 December 2020 8.Appendix 4.2 - Directional Signing to Access 10I -190608-D04 Rev A HCV/AIL Traffic Routing and Temporary Traffic Management Stages 7, 8 and 10 submitted to the Local Planning Authority on 8 December 2020 9.Appendix 5.1 - Dilapidations Scoping Correspondence submitted to the Local Planning Authority on 8 December 2020 |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Covering Letter | 627 kb | 02/12/2021 | |
| Application Form | 167 kb | 02/12/2021 | |
| Consultee Responses | |||
| Consultee response - Engineering Team (Highways) | 47 kb | 19/01/2022 | |
| Decision | |||
| Compliance Decision Notice R20211034cd | 120 kb | 25/01/2022 | |
| Officer Report | |||
| Compliance Officer Report R20211034cd | 113 kb | 25/01/2022 | |
| Superseded | |||
| Requirement 24 - Highways Access Management Plan - SUPERSEDED | 522 kb | 02/12/2021 | |
| Supporting Documentation | |||
| Requirement 24 - Hamp Appendix 2.1 | 1667 kb | 02/12/2021 | |
| Requirement 24 - Hamp Appendix 5.1 | 955 kb | 02/12/2021 | |
| Requirement 24 - Hamp Appendix 3.1 | 923 kb | 02/12/2021 | |
| Requirement 24 - Hamp Appendix 2.2 | 1565 kb | 02/12/2021 | |
| Requirement 24 - Hamp Appendix 4.1 | 1751 kb | 02/12/2021 | |
| Requirement 24 - Hamp Appendix 4.2 | 8731 kb | 02/12/2021 | |
| Requirement 24 - Highways Access Management Plan - AMENDED 08 12 2021 | 365 kb | 08/12/2021 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 07/12/2021 | - |