R/2021/1032/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 28 (CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN) FOR STAGE 5 PART 2 OF THE ONSHORE WORKS FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL PLANNING DESCRIPTION...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIM
Applicant's Address
- - 1 FORBURY PLACE 43 FORBURY ROAD READING RG1 3JH
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER SUITE 1C SWINEGATE COURT EAST 3 SWINEGATE YORK YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
02/12/2021
Date Valid
02/12/2021
Expiry
27/01/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
25/01/2022
Decision Level
-

Conditions table
# Condition Details
1 Construction environmental management plan 28.—(1) Before the commencement of each stage of the onshore works, a construction environmental management plan (“CEMP”) for that stage, drafted in accordance with the principles set out in the CoCP, must be submitted to and approved by the relevant planning authority. (2) All remediation, construction and commissioning works must be undertaken in accordance with each relevant CoCP and CEMP. “(3) For the avoidance of doubt, each CEMP approved under paragraph 1 of this requirement may cover one or more stages of the onshore works.”.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Covering Letter 288 kb 02/12/2021
Application Form 167 kb 02/12/2021
Consultee Responses
Consultee response - Public Rights of Way 446 kb 07/12/2021
Consultee response - Environmental Protection (Contaminated Land) 15 kb 15/12/2021
Consultee response - Environmental Protection (Nuisance) 15 kb 15/12/2021
Consultee Response - Natural England 78 kb 21/12/2021
Consultee response - Engineering Team (Highways) 47 kb 19/01/2022
Decision
Compliance Decision Notice R20211032cd 120 kb 25/01/2022
Supporting Documentation
Requirement 28 - Sowf Discharge Of Requirements Req 28 Contruction Environmental Management Plan Cemp Dco Stage 5 Part 2 + Tcpa Stages Final 2014 kb 02/12/2021
Requirement 28 - Cemp Appendix 3.1 Cable Preparation Works Part 2 133 kb 02/12/2021
Requirement 28 - Cemp Appendix 1.2 Cable Preparation Works Part 2 208 kb 02/12/2021
Requirement 28 - Cemp Appendix 3.2 Cable Preparation Works Part 2 465 kb 02/12/2021
Requirement 28 - Cemp Appendix 1.1 Cable Preparation Works Part 2 1122 kb 02/12/2021
Requirement 28 - Cemp Appendix 2.2 Cable Preparation Works Part2 4162 kb 02/12/2021
Requirement 28 - Cemp Appendix 2.1 Cable Preparation Work Part 2 4064 kb 02/12/2021
Requirement 28 - Cemp Appendix 2.3 Cable Preparation Works Part 2 6107 kb 02/12/2021
Consultee Name Date Letter Sent Consultation Expiry Date
Condition Discharge - David Pedlow 07/12/2021 -
Engineering Team (Highways) 07/12/2021 -
Environmental Protection Team 07/12/2021 -
Environmental Protection Team 07/12/2021 -
Natural England 07/12/2021 -
Public Rights of Way 07/12/2021 -