R/2021/1016/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 32 (CONSTRUCTION TRAFFIC ROUTING & MANAGEMENT PLANS) FOR STAGE 5 PART 2 FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELO...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIM
Applicant's Address
- - 1 FORBURY PLACE 43 FORBURY ROAD READING RG1 3JH
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER SUITE 1C SWINEGATE COURT EAST 3 SWINEGATE YORK YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
01/12/2021
Date Valid
01/12/2021
Expiry
26/01/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
25/01/2022
Decision Level
-

Conditions table
# Condition Details
1 Requirement 32 32.—(1) No stage of the onshore works may commence until for that stage, written details of a construction traffic management plan (“CTMP”) and a construction travel plan (“CTP”), to be used for the management of construction traffic for that stage, has been submitted to and approved by the relevant planning authority and Highways England. (2) Each CTMP and CTP must include details (including agreed routes) for abnormal indivisible loads (“AILs”) that may be delivered by road (or confirmation that no AILs are required for construction of the authorised development), and the approved details must be adhered to at all times when AILs are transported to or from the authorised development by road (3) Notices must be erected and maintained throughout the period of construction at construction site exits, in accordance with the CTMP, indicating to drivers the routes agreed by the relevant planning authority for traffic entering and leaving sites. (4) For the avoidance of doubt, each scheme approved under paragraph (1) of this requirement may cover one or more stages of the onshore works.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Covering Letter 145 kb 01/12/2021
Application Form 167 kb 01/12/2021
Decision
Compliance Decision Notice R20211016cd 122 kb 25/01/2022
Officer Report
Compliance Officer Report R20211016cd 122 kb 25/01/2022
Superseded
CTMP Appendix 1.1 Cable Preparation Works Part 2 - SUPERSEDED 1412 kb 01/12/2021
CTP Appendix 4.1 Cable Preparation Works Part 2 - SUPERSEDED 1419 kb 01/12/2021
Supporting Documentation
Requirement 32 - Construction Traffic Management Plan 548 kb 01/12/2021
CTMP Appendix 1.2 Cable Preparation Works Part 2 1220 kb 01/12/2021
CTMP Appendix 1.3 Cable Preparation Works Part 2 5167 kb 01/12/2021
CTMP Appendix 2.1 Cable Preparation Work Part 2 4049 kb 01/12/2021
CTMP Appendix 2.2 Cable Preparation Works Part2 4154 kb 01/12/2021
CTMP Appendix 2.3 Cable Preparation Works Part 2 6100 kb 01/12/2021
CTMP Appendix 4.1 Cable Preparation Works Part 2 Reduced 1510 kb 01/12/2021
CTMP Appendix 4.2 Cable Preparation Works Part 2 Reduced 1644 kb 01/12/2021
Requirement 32 - Construction Travel Plan 582 kb 01/12/2021
CTP Appendix 2.1 Cable Preparation Work Part 2 4064 kb 01/12/2021
CTP Appendix 2.2 Cable Preparation Works Part2 4161 kb 01/12/2021
CTP Appendix 2.3 Cable Preparation Works Part 2 6107 kb 01/12/2021
CTP Appendix 4.3 Cable Preparation Works Part 2 1234 kb 01/12/2021
CTP Appendix 4.2 Cable Preparation Works Part 2 6640 kb 01/12/2021
CTP Appendix 4.4 Cable Preparation Works Part 2 8014 kb 01/12/2021
CTP Appendix 4.5 Cable Preparation Works Part 2 1532 kb 01/12/2021
CTP Appendix 4.1 Cable Preparation Works Part 2 - AMENDED 08 12 2021 2654 kb 09/12/2021
CTMP Appendix 1.1 Cable Preparation Works Part 2 - AMENDED 08 12 2021 2647 kb 09/12/2021
Consultee response - Engineering Team (Highways) 447 kb 14/01/2022
Consultee Name Date Letter Sent Consultation Expiry Date
Engineering Team (Highways) 02/12/2021 -