R/2021/0994/CD

Planning Application Details

Location
SOFIA ONSHORE CONVERTER STATION (OCS) AND ASSOCIATED WORKS NEAR LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 32 (CONSTRUCTION TRAFFIC ROUTING & MANAGEMENT PLANS) IN RELATION TO STAGES 11, 13 AND 16 OF THE ONSHORE WORKS UNDER THE DOGGER BANK TEESSIDE A&B OFFSHORE WIND FARM ORDER 2015 AS (AMENDED) (THE 'DCO') IN RELATION TO SOFIA OFFSHORE WIND FARM ('PROJECT B')
Application Type
Condition Discharge
Status
Decision
Parish(es)
Applicant
SOFIA OFFSHORE WIND FARM LIMITED
Applicant's Address
MS KIM GAULD CLARK WINDMILL HILL BUSINESS PARK WHITEHILL WAY SWINDON SN5 6PB
Agent
RPS Consulting Services Ltd
Agent's Address
CLARE RUSSELL 20 WESTERN AVENUE MILTON PARK MILTON ABINGDON OX14 4SH
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
24/11/2021
Date Valid
25/11/2021
Expiry
20/01/2022
Consultation Expiry
-
associated_bldreg
-
Decision
-
Decision Date
-
Decision Level
-

Conditions table
# Condition Details
1 Requirement 32 32.—(1) No stage of the onshore works may commence until for that stage, written details of a construction traffic management plan (“CTMP”) and a construction travel plan (“CTP”), to be used for the management of construction traffic for that stage, has been submitted to and approved by the relevant planning authority and Highways England. (2) Each CTMP and CTP must include details (including agreed routes) for abnormal indivisible loads (“AILs”) that may be delivered by road (or confirmation that no AILs are required for construction of the authorised development), and the approved details must be adhered to at all times when AILs are transported to or from the authorised development by road (3) Notices must be erected and maintained throughout the period of construction at construction site exits, in accordance with the CTMP, indicating to drivers the routes agreed by the relevant planning authority for traffic entering and leaving sites. (4) For the avoidance of doubt, each scheme approved under paragraph (1) of this requirement may cover one or more stages of the onshore works.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 168 kb 24/11/2021
Consultee Responses
Consultee response - Engineering Team (Highways) 453 kb 06/01/2022
Decision
Compliance Decision Notice R20210994cd 172 kb 18/01/2022
Officer Report
Officer Report 106 kb 19/01/2022
Plans
Construction Travel Plan 617 kb 24/11/2021
Construction Traffic Management Plan 577 kb 24/11/2021
Construction Travel Plan Appendix Document 3687 kb 24/11/2021
Construction Traffic Management Plan Appendix 5242 kb 25/11/2021
Supporting Documentation
Covering Letter 231 kb 24/11/2021
Consultee Name Date Letter Sent Consultation Expiry Date
Engineering Team (Highways) 29/11/2021 -