Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
RESUBMISSION OF DETAILS FOR REQUIREMENT 18 (ONSHORE PHASING PLAN) STAGES 5 & 7 OF THE ONSHORE WORKS FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS S...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
PROJCO3 & SOWFL
Applicant's Address
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG1 3JH
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER
SUITE 1C
SWINEGATE COURT EAST
3 SWINEGATE
YORK
YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
16/11/2021
Date Valid
16/11/2021
Expiry
11/01/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
06/01/2022
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (18) The onshore works must not commence until a written scheme setting out the phasing of construction of each stage of the onshore works has been submitted to and approved by the relevant planning authority. (2) The scheme must be implemented as approved. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 169 kb | 16/11/2021 | |
| Decision | |||
| Compliance Decision Notice R20210963cd | 174 kb | 06/01/2022 | |
| Supporting Documentation | |||
| Requirement 18 - Covering Letter | 141 kb | 16/11/2021 | |
| Requirement 18 - Onshore Phasing Plan | 6105 kb | 16/11/2021 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Condition Discharge - David Pedlow | 17/11/2021 | - |