Location
SOFIA ONSHORE CONVERTER STATION (OCS) AND ASSOCIATED WORKS NEAR LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 25 (SURFACE AND FOUL WATER DRAINAGE) FOR STAGE 11 OF THE ONSHORE WORKS UNDER THE DOGGER BANK TEESSIDE A&B OFFSHORE WIND FARM ORDER 2015 (AS AMENDED) (THE 'DCO') IN RELATION TO SOFIA OFFSHORE WIND FARM ('PROJECT B')
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
SOFIA OFFSHORE WIND FARM LIMITED
Applicant's Address
MS KIM GAULD CLARK
WINDMILL HILL BUSINESS PARK
WHITEHILL WAY
SWINDON
SN5 6PB
Agent
RPS Consulting Services Ltd
Agent's Address
CLARE RUSSELL
20 WESTERN AVENUE
MILTON PARK
MILTON
ABINGDON
OX14 4SH
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
08/11/2021
Date Valid
08/11/2021
Expiry
03/01/2022
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
21/12/2021
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (1) No stage of the onshore works may commence until written details of the surface and (if any) foul water drainage system (including means of pollution control) for that stage have, following consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the relevant planning authority. (2) The surface water drainage system works must restrict surface water discharge to no more than the greenfield run-off rate (1.62 litres per second) in line with the recommendations of the flood risk assessment (Appendix B to Chapter 24 of the environmental statement). (3) The submitted details must— (a) provide information about the design storm period and intensity, the method employed to delay and control the surface water discharged from the site (surface water drainage scheme); (b) include a timetable for implementation (foul and surface water schemes); and (c) provide a management and maintenance plan for the lifetime of the proposed schemes (foul and surface water management) |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineers (Local Lead Flood Authority) | 09/11/2021 | - |
| Environment Agency | 09/11/2021 | - |
| Northumbrian Water Ltd | 09/11/2021 | - |