Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
RESUBMISSION OF DETAILS FOR REQUIREMENT 35 (1) (2) (3) (ECOLOGICAL MANAGEMENT PLAN) FOR STAGES 5; 6 & 7 OF THE ONSHORE WORKS IN RELATION DOGGER BANK C WIND FARM (FORMERLY TEESSIDE A OFFSHORE WIND FARM) (‘PROJECT A’) AND SOFIA OFFSHORE WIND FARM (FORMERLY TEESSIDE B OFFSHORE WIND FARM) (‘PROJECT B’)...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIM
Applicant's Address
- -
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG1 3JH
Agent
Arcus Consulting
Agent's Address
MR TIM WHEELER
144 W GEORGE ST, 7TH FLOOR
SWINEGATE COURT EAST
3 SWINEGATE
GLASGOW
G2 2HG
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
21/10/2021
Date Valid
21/10/2021
Expiry
16/12/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
23/11/2021
Decision Level
-
No Conditions Found For This Application
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Covering Letter | 141 kb | 21/10/2021 | |
| Application Form | 168 kb | 21/10/2021 | |
| Consultee Responses | |||
| Consultee response - Natural Heritage Manager | 449 kb | 26/10/2021 | |
| Consultee Response - Natural England | 84 kb | 12/11/2021 | |
| Decision | |||
| Compliance Decision Notice R20210884cd | 169 kb | 23/11/2021 | |
| Officer Report | |||
| Compliance Officer Report R20210884cd(1) | 117 kb | 23/11/2021 | |
| Supporting Documentation | |||
| Ecological Management Plan | 1722 kb | 21/10/2021 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Natural England | 25/10/2021 | - |
| Natural Heritage Manager | 25/10/2021 | - |