R/2021/0751/CD

Planning Application Details - Official Consultation has expired.

Location
LAND SOUTH OF WOODLEA OFF VICTORIA TERRACE SALTBURN TS12 1JH
Proposal
DISCHARGE OF CONDITIONS 3; 4; 5; 6 ; 8; 10; 11; 12 & 15 OF PLANNING PERMISSION R/2021/0040/CA FOR A DETACHED TWO STOREY DWELLING WITH ROOMS IN THE ROOF AND ATTACHED DOUBLE GARAGE WITH BEDROOM ABOVE
Application Type
Condition Discharge
Status
Approved
Parish(es)
Saltburn, Marske and New Marske CP
Applicant
JAMBAY BUILD
Applicant's Address
LAND AT WOODLEA, VICTORIA TERRACE SALTBURN BY THE SEA TS12 1JH
Agent
G R HENDERSON ARCHITECTURAL DESIGN
Agent's Address
MR GORDON HENDERSON 20 CONWAY ROAD REDCAR TS10 2EN
Agent's work phone
Agent's email
Case Officer
Mrs H Conti
Case Officer Telephone
01287 612340
Case Officer Email
helen.conti@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
02/09/2021
Date Valid
02/09/2021
Expiry
28/10/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
15/10/2021
Decision Level
-

Conditions table
# Condition Details
1 Prior to the commencement of development plans showing the existing and proposed ground levels over the site together with finished floor levels and maximum building heights shall be submitted to and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure a satisfactory relationship between existing and proposed buildings in accordance with policy SD4 of the Local Plan. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as construction activity and site preparation can change existing levels resulting in increased ground levels which the authority needs to consider.
2 Notwithstanding the details contained within the landscaping plan, the development hereby permitted shall not be commenced until such time as a scheme to dispose of foul and surface water has been submitted to, and approved in writing by, the Local Planning Authority. The scheme shall be implemented as approved. REASON To prevent pollution of the water environment REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation
3 Unless otherwise agreed by the Local Planning Authority in writing, development other than that required to be carried out as part of an approved scheme of remediation must not commence until parts (a) to (c) have been complied with. If unexpected contamination is found after development has begun, development must be halted on that part of the site affected by the unexpected contamination to the extent specified by the Local Planning Authority in writing until condition (e) has been complied with in relation to that contamination. (a) Site Characterisation An investigation and risk assessment, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, whether or not it originates on the site. The contents of the scheme are subject to the approval in writing of the Local Planning Authority. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) an assessment of the potential risks to: • human health, • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, • adjoining land, • groundwaters and surface waters, • ecological systems, • archeological sites and ancient monuments; (iii) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with Environment Agency’s Land Contamination Risk Management Guidance (b) Submission of Remediation Scheme A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. (c) Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. (d) Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of part (a) and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of part (b), which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. (e) Long Term Monitoring and Maintenance A monitoring and maintenance scheme to include monitoring the long-term effectiveness of the proposed remediation over a period of 10 years, and the provision of reports on the same must be prepared, both of which are subject to the approval in writing of the Local Planning Authority. Following completion of the measures identified in that scheme and when the remediation objectives have been achieved, reports that demonstrate the effectiveness of the monitoring and maintenance carried out must be produced, and submitted to the Local Planning Authority. This must be conducted in accordance with Environment Agency’s Land Contamination Risk Management Guidance REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to land contamination details which are often the first works on site and relate to site preparation.
4 Prior to commencement of construction, a Construction Environmental Management Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide the following; i) The parking of vehicles for site operatives and visitors; ii) Loading and unloading of plant and materials; iii) Storage of plant and materials used in constructing the development; iv) The erection and maintenance of security hoarding including decorative displays; v) Wheel washing facilities; vi) Measures to control the emission of noise dust and vibration during the construction period. vii) A scheme for recycling/disposing of waste resulting from demolition and construction works. REASON: To protect the amenity of nearby residents and in the interests of highway safety.
5 Prior to installation, full details and/or samples of rainwater gutters and pipes, fascia boards, windows and doors, to be used in the external elevations shall be submitted to and approved in writing by the local planning authority. The development shall be completed in accordance with the approved details. REASONS: To safeguard the special character of the conservation area as required by Policy HE1 of the adopted Local Plan.
6 Notwithstanding details shown on submitted plans, prior to the first occupation of the development, hereby approved, boundary walls (including the retaining wall) and fences shall have been erected in accordance with a scheme that has first been submitted to and agreed in writing with the Local Planning Authority. The boundary walls and fences shall thereafter be maintained unless the express consent of the Local Planning Authority is given. REASON: To ensure that any boundary treatments would accord with policy SD4 of the Redcar and Cleveland Local Plan by respecting the character of the site and the surroundings and raising no significant adverse impact on neighbouring occupiers.
7 Notwithstanding details shown on submitted plans, prior to (occupation of the completed dwelling on the site / occupation of the building hereby approved) a landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority. The details shall include size, type and species along with hard surface treatment to the remainder of the site and a programme of works. The development shall be completed in accordance with the approved details. REASON: To ensure that the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan.
8 Prior to installation at the site any external lighting details shall have first been the submitted to and approved in writing by the Local Planning Authority. Only the approved scheme of lighting shall be installed at the site. REASON: In the interests of amenity in accordance with Local Plan Policy SD3.
9 No site clearance or building operations shall commence on the site until a protective fence(s) is installed in line with the requirements of the British Standard 5837 around the retained trees along the western, southern and eastern boundary of the site. The protective fence(s) shall be in place before any equipment, machinery or materials are brought on to the site for the purposes of the development and shall be maintained until all equipment, machinery and surplus materials have been removed from the site. Nothing shall be stored or placed in any area fenced in accordance with this condition and the ground levels within those areas shall not be altered, nor shall any excavation be made, without the written consent of the Local Planning Authority. REASON: To protect the retained trees from damage during construction, including all ground works and works that may be required by other conditions, and in recognition of the contribution which the retained tree(s) give(s) and will continue to give to the amenity of the area.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 167 kb 02/09/2021
Consultee Responses
Consultee response - Environmental Protection (Contaminated Land) 189 kb 22/09/2021
Consultee response - Environmental Protection (Nuisance) 238 kb 23/09/2021
Decision
Compliance Decision Notice 464 kb 15/10/2021
Officer Report
Compliance Officer Report 328 kb 15/10/2021
Plans
Condition No. 6 - CEMP 126 kb 02/09/2021
Condition No. 3 - Levels - Pre-commencement 250 kb 02/09/2021
Condition No. 8 - Samples of windows, doors etc. 169 kb 02/09/2021
Condition No. 3 - Levels - Pre-Commencement 103 kb 02/09/2021
Condition No. 8 - Samples of Windows, doors etc. 120 kb 02/09/2021
Condition No. 8 - Samples of windows, doors etc. - SUPERSEDED 298 kb 02/09/2021
Condition No. 8 - Samples of Windows, doors etc. - SUPERSEDED 344 kb 02/09/2021
Location and Site Plan 168 kb 02/09/2021
Conditions 4; 11 & 12 - Foul & Surface Water Drainage; Boundary Treatments & Landscaping 293 kb 02/09/2021
Condition No. 3 - Levels - Site Section - SUPERSEDED 123 kb 08/10/2021
Condition No. 3 - Levels _ Site Section - AMENDED 14 10 2021 121 kb 14/10/2021
Condition No. 8 - Samples of Windows, doors etc. - AMENDED 14 10 2021 382 kb 14/10/2021
Condition No. 8 - Samples of Windows, doors etc. - AMENDED 14 10 2021 319 kb 14/10/2021
Supporting Documentation
R/2021/0040/CA Decision Notice 282 kb 02/09/2021
Condition No. 15 including List of Conditions 326 kb 02/09/2021
Condition No. 10 - Tree Protection 1041 kb 02/09/2021
Condition No. 6 - CEMP 474 kb 02/09/2021
Condition No. 5 - Contaminated Land - Pre-Commencement 94518 kb 02/09/2021
Consultee Name Date Letter Sent Consultation Expiry Date
Aboricultural Officer 08/09/2021 -
Councillor C Hannaway (SALTBURN) 08/09/2021 -
Councillor P Thomson (SALTBURN) 08/09/2021 -
Councillor Stuart Smith (SALTBURN) 08/09/2021 -
Engineering Team (Highways) 08/09/2021 -
Engineers (Local Lead Flood Authority) 08/09/2021 -
Environmental Protection Team 08/09/2021 -
Northumbrian Water Ltd 08/09/2021 -
Strategic Planning Team (CA & LB) 08/09/2021 -