R/2021/0566/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 25 (1) (2) (3) (SURFACE AND FOUL WATER DRAINAGE) FOR STAGE 7 FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS SP...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
PROJCO3 & SOWFL
Applicant's Address
- - 1 FORBURY PLACE 43 FORBURY ROAD READING RG1 3JH
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER SUITE 1C SWINEGATE COURT EAST 3 SWINEGATE YORK YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
05/07/2021
Date Valid
06/07/2021
Expiry
31/08/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
31/08/2021
Decision Level
-

No Conditions Found For This Application

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 167 kb 05/07/2021
Consultee Responses
Consultee response - Environment Agency 209 kb 08/07/2021
Consultee response - Northumbrian Water 375 kb 23/07/2021
Consultee response - Engineers (Local Lead Flood Authority) 453 kb 04/08/2021
Decision
Compliance Decision Notice R20210566cd 129 kb 31/08/2021
Officer Report
Compliance Officer Report R20210566cd 81 kb 31/08/2021
Supporting Documentation
Requirement 25 - Foul and Surface Water Drainage Scheme 748 kb 05/07/2021
Requirement 25 - Drainage Construction Details Sheet 3 201 kb 05/07/2021
Requirement 25 - Drainage Construction Details Sheet 1 276 kb 05/07/2021
Requirement 25 - Drainage Construction Details Sheet 2 298 kb 05/07/2021
Requirement 25 - Enabling Works Platform Sections Sheet 2 of 2 264 kb 05/07/2021
Requirement 25 - Enabling Works Platform Sections Sheet 1 of 2 288 kb 05/07/2021
Requirement 25 - Enabling Works Construction Details 831 kb 05/07/2021
Requirement 25 - Operational Drainage Layout 968 kb 05/07/2021
Requirement 25 - Enabling Works Platform Layout 1056 kb 05/07/2021
Requirement 25 - Enabling Works Drainage Layout 1329 kb 05/07/2021
Requirement 25 - Drainage Design Statement 7179 kb 05/07/2021
Covering Letter 512 kb 06/07/2021
Consultee Name Date Letter Sent Consultation Expiry Date
Engineers (Local Lead Flood Authority) 08/07/2021 -
Environment Agency 08/07/2021 -
Northumbrian Water Ltd 08/07/2021 -