R/2021/0565/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 25 (1) (2) (3) (SURFACE AND FOUL WATER DRAINAGE) FOR STAGE 10 FOR TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS S...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
SOFIA OFFSHORE WIND FARM LIMITED
Applicant's Address
KIM CLARK WINDMILL HILL BUSINESS PARK WHITEHILL WAY SWINDON SN5 6PB
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER SUITE 1C SWINEGATE COURT EAST 3 SWINEGATE YORK YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
05/07/2021
Date Valid
05/07/2021
Expiry
30/08/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
31/08/2021
Decision Level
-

Conditions table
# Condition Details
1 (1) No stage of the onshore works may commence until written details of the surface and (if any) foul water drainage system (including means of pollution control) for that stage have, following consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the relevant planning authority. (2) The surface water drainage system works must restrict surface water discharge to no more than the greenfield run-off rate (1.62 litres per second) in line with the recommendations of the flood risk assessment (Appendix B to Chapter 24 of the environmental statement). (3) The submitted details must— (a) provide information about the design storm period and intensity, the method employed to delay and control the surface water discharged from the site (surface water drainage scheme); (b) include a timetable for implementation (foul and surface water schemes); and (c) provide a management and maintenance plan for the lifetime of the proposed schemes (foul and surface water management)

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 167 kb 05/07/2021
Consultee Responses
Consultee response - Environment Agency 210 kb 08/07/2021
Consultee response - Northumbrian Water 375 kb 23/07/2021
Consultee response - Engineers (Local Lead Flood Authority) 454 kb 04/08/2021
Decision
Compliance Decision Notice R20210565cd 129 kb 31/08/2021
Officer Report
Compliance Officer Report R20210565cd 121 kb 31/08/2021
Supporting Documentation
Covering letter 503 kb 05/07/2021
Requirement 25 - Foul and Surface Water Drainage Scheme 748 kb 05/07/2021
Requirement 25 - Enabling Works Platform Sections Sheet 1 288 kb 05/07/2021
Requirement 25 - Drainage Construction Details Sheet 3 201 kb 05/07/2021
Requirement 25 - Enabling Works Platform Sections Sheet 2 264 kb 05/07/2021
Requirement 25 - Drainage Construction Details Sheet 1 276 kb 05/07/2021
Requirement 25 - Drainage Construction Details Sheet 2 298 kb 05/07/2021
Requirement 25 - Enabling Works Construction Details 831 kb 05/07/2021
Requirement 25 - Operational Drainage Layout 968 kb 05/07/2021
Requirement 25 - Enabling Works Platform Layout 1056 kb 05/07/2021
Requirement 25 - Enabling Works Drainage Layout 1329 kb 05/07/2021
Requirement 25 - Site Drainage Design Statement 7179 kb 05/07/2021
Consultee Name Date Letter Sent Consultation Expiry Date
Engineers (Local Lead Flood Authority) 08/07/2021 -
Environment Agency 08/07/2021 -
Northumbrian Water Ltd 08/07/2021 -