Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
DISCHARGE OF CONDITION 10 (CEMP) OF PLANNING PERMISSION R/2020/0355/FFM FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND FARMS AND LACKENBY SUBSTATION AND ASSOCIATED TEMPORARY ...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Saltburn, Marske and New Marske CP
Applicant
PROJCO3 & SOWFL
Applicant's Address
MS VICTORIA RIDYARD
1 FORBURY PLACE
43 FORBURY ROAD
READING
RG1 3JH
Agent
Royal HaskoningDHV
Agent's Address
CLAIRE DAVIES
ROYAL HASKONINGDHV
9TH FLOOR MANCHESTER ONE
53 PORTLAND STREET
MANCHESTER
M1 3LF
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
05/07/2021
Date Valid
05/07/2021
Expiry
30/08/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITIONAL CONSENT
Decision Date
31/08/2021
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (1) Before the commencement of each stage, a construction environmental management plan (“CEMP”) for that stage, drafted in accordance with the principles set out in the CoCP, must be submitted to and approved by the local planning authority. (2) All remediation, construction and commissioning works must be undertaken in accordance with each relevant CoCP and CEMP. (3) For the avoidance of doubt, each CEMP approved under paragraph 1 of this condition may cover one or more stages. REASON: In the interest of neighbour amenity, highways safety and protection of ecology value in accordance with policies SD4 and N4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as it relates to construction details which are often the first works on site and relate to site preparation. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 168 kb | 05/07/2021 | |
| Consultee Responses | |||
| Consultee response - Environmental Protection (Contaminated Land) | 239 kb | 23/07/2021 | |
| Consultee response - Environmental Protection (Nuisance) | 239 kb | 23/07/2021 | |
| Consultee response - Engineering Team (Highways) | 46 kb | 10/08/2021 | |
| Decision | |||
| Compliance Decision Notice R20210563cd Sofia | 117 kb | 31/08/2021 | |
| Compliance Decision Notice R20210563cddogger | 117 kb | 31/08/2021 | |
| Supporting Documentation | |||
| Condition No. 10 - Construction Environmental Management Plan | 660 kb | 05/07/2021 | |
| Condition No. 10 - Construction Environmental Management Plan - Appendices | 8875 kb | 05/07/2021 | |
| Covering Letter | 407 kb | 05/07/2021 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 06/07/2021 | - |
| Environmental Protection Team | 06/07/2021 | - |