Location
DWELLINGS AND LAND AT CAERNARVON CLOSE, SOMERSET ROAD, CHEDDAR CLOSE, AVONDALE CLOSE, MONMOUTH ROAD, ABERDARE ROAD, BRIDGEND CLOSE,
GRANGETOWN
Proposal
DISCHARGE OF CONDITIONS 3, 4, 5, 6, 7, 8 & 9 OF PART A OF PLANNING PERMISSION R/2019/0403/FFM AND DISCHARGE OF CONDITIONS 3, 4, 5, 6, 7, 8 & 9 OF PART B OF OUTLINE PERMISSION R/2019/0403/FFM
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
BEYOND HOUSING
Applicant's Address
MS FRANCES BARLOW
14 ENNIS SQUARE
DORMANSTOWN
TS10 5JR
Agent
LOGIC ARCHITECTURE
Agent's Address
LOGIC ARCHITECTURE
BOHO ONE
BRIDGE STREET WEST
BOHO ZONE
MIDDLESBROUGH
TS2 1AE
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
02/03/2021
Date Valid
10/03/2021
Expiry
15/06/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
20/09/2021
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | Prior to any works to the external elevations of the existing dwellings details of the external materials to be used (including samples) shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan. |
| 2 | Prior to the construction of the final surface treatment, for any hard surfaced areas, details of the materials to be used shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan. |
| 3 | Prior to the commencement of the development, or in such extended time as may be agreed in writing with the Local Planning Authority, details shall be submitted and approved of the surface water drainage scheme and the development shall be completed in accordance with the approved scheme. The design of the drainage scheme shall include; (i) Restriction of surface water greenfield run-off rates (QBAR value) with sufficient storage within the system to accommodate a 1 in 30 year storm. (ii)The method used for calculation of the existing greenfield run-off rate shall be the ICP SUDS method. The design shall also ensure that storm water resulting from a 1 in 100 year event, plus climate change surcharging the system, can be stored on site with minimal risk to persons or property and without overflowing into drains, local highways or watercourses. (iii) Full Micro Drainage design files (mdx files) including a catchment plan (iv) The flow path of flood waters for the site as a result on a 1 in 100 year event plus climate change REASON: To ensure the development is supported by a suitably designed surface water disposal infrastructure scheme and to minimise the risk flooding in the locality. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 4 | Prior to the commencement of the development, or in such extended time that may be agreed with the Local Planning Authority, details of a Surface Water Drainage Management Plan shall be submitted and approved by the Local Planning Authority. The Management Plan shall include; (i) The timetable and phasing for construction of the drainage system (ii) Details of any control structure(s) (iii) Details of surface water storage structures (iv) Measures to control silt levels entering the system and out falling into any watercourse during the construction process The development shall, in all respects, be carried out in accordance with the approved Management Plan. REASON: To ensure the development is supported by an appropriately designed surface water disposal infrastructure scheme and to minimise the risk of increased flooding and contamination of the system during the construction process. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 5 | The development shall not be occupied until a Management & Maintenance Plan for the surface water drainage scheme has been submitted to and approved by the Local planning Authority; the plan shall include details of the following; (i) A plan clearly identifying the sections of surface water system that are to be adopted (ii) Arrangements for the short and long term maintenance of the SuDS elements of the surface water system REASON: To ensure that the surface water drainage infrastructure is maintained to minimise the risk flooding in the locality. |
| 6 | Prior to commencement of demolition, construction or refurbishment works, a Consturction Environmental Method Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide the following; i) The parking of vehicles for site operatives and visitors; ii) ii) Loading and unloading of plant and materials; iii) Storage of plant and materials used in constructing the development; iv) The erection and maintenance of security hoarding including decorative displays; v) Wheel washing facilities; vi) Methods of demolition; vii) Measures to control the emission of noise dust and vibration during the construction period. viii) A scheme for recycling/disposing of waste resulting from demolition and construction works. REASON: To protect the amenity of nearby residents and in the interests of highway safety. REASON FOR PRE COMMENCMENT: The details required for the CEMP relate to setting up of the site and early construction activities. |
| 7 | Within six months of the date of this permission a landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority. The details shall include size, type and species and a programme of work. The development shall be completed in accordance with the approved details. REASON: To ensure that the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan. |
| 8 | Development shall not commence until a detailed scheme for the disposal of foul water from the development hereby approved has been submitted to and approved in writing by the Local Planning Authority in consultation with Northumbrian Water and the Lead Local Flood Authority. Thereafter the development shall take place in accordance with the approved details. REASON: To prevent the increased risk of flooding from any sources in accordance with the NPPF. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 9 | Prior to the commencement of the development, or in such extended time as may be agreed in writing with the Local Planning Authority, details shall be submitted and approved of the surface water drainage scheme and the development shall be completed in accordance with the approved scheme. The design of the drainage scheme shall include; (i) Restriction of surface water greenfield run-off rates (QBAR value) with sufficient storage within the system to accommodate a 1 in 30 year storm. (ii)The method used for calculation of the existing greenfield run-off rate shall be the ICP SUDS method. The design shall also ensure that storm water resulting from a 1 in 100 year event, plus climate change surcharging the system, can be stored on site with minimal risk to persons or property and without overflowing into drains, local highways or watercourses. (iii) Full Micro Drainage design files (mdx files) including a catchment plan (iv) The flow path of flood waters for the site as a result on a 1 in 100 year event plus climate change REASON: To ensure the development is supported by a suitably designed surface water disposal infrastructure scheme and to minimise the risk flooding in the locality. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 10 | Prior to the commencement of the development, or in such extended time that may be agreed with the Local Planning Authority, details of a Surface Water Drainage Management Plan shall be submitted and approved by the Local Planning Authority. The Management Plan shall include; (i) The timetable and phasing for construction of the drainage system (ii) Details of any control structure(s) (iii) Details of surface water storage structures (iv) Measures to control silt levels entering the system and out falling into any watercourse during the construction process The development shall, in all respects, be carried out in accordance with the approved Management Plan. REASON: To ensure the development is supported by an appropriately designed surface water disposal infrastructure scheme and to minimise the risk of increased flooding and contamination of the system during the construction process. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 11 | The development shall not be occupied until a Management & Maintenance Plan for the surface water drainage scheme has been submitted to and approved by the Local planning Authority; the plan shall include details of the following; (i) A plan clearly identifying the sections of surface water system that are to be adopted (ii) Arrangements for the short and long term maintenance of the SuDS elements of the surface water system REASON: To ensure that the surface water drainage infrastructure is maintained to minimise the risk flooding in the locality. |
| 12 | Prior to commencement of demolition, construction or refurbishment works, a Construction Environmental Management Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide the following; i) The parking of vehicles for site operatives and visitors; ii) ii) Loading and unloading of plant and materials; iii) Storage of plant and materials used in constructing the development; iv) The erection and maintenance of security hoarding including decorative displays; v) Wheel washing facilities; vi) Methods of demolition; vii) Measures to control the emission of noise dust and vibration during the construction period. viii) A scheme for recycling/disposing of waste resulting from demolition and construction works. REASON: To protect the amenity of nearby residents and in the interests of highway safety. REASON FOR PRE COMMENCEMENT: The details required for the CEMP relate to setting up of the site and early construction activities. |
| 13 | Prior to any development above damp proof course details of the external materials to be used in the carrying out of this permission (including samples) shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan. |
| 14 | Prior to the construction of the final surface treatment, for any hard surfaced areas, details of the materials to be used shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 12/03/2021 | - |
| Engineers (Local Lead Flood Authority) | 12/03/2021 | - |
| Environmental Protection Team | 12/03/2021 | - |
| Northumbrian Water Ltd | 12/03/2021 | - |