R/2021/0119/CD

Planning Application Details - Official Consultation has expired.

Location
LAND AT ALBION TERRACE GUISBOROUGH
Proposal
DISCHARGE OF CONDITIONS 3; 4; 6; 7; 8; 10; 11; 12, OF PLANNING PERMISSION R/2017/0910/CA FOR 3 DETACHED DWELLINGS
Application Type
Condition Discharge
Status
Approved
Parish(es)
Guisborough CP
Applicant
MR A LITTLE
Applicant's Address
C/O AGENT
Agent
STOVELL & MILLWATER
Agent's Address
5 BRENTNALL CENTRE BRENTNALL STREET MIDDLESBROUGH TS1 5AP
Agent's work phone
01642 232397
Agent's email
planning@davidstovellandmillwater.co.uk
Case Officer
Mrs C Griffiths
Case Officer Telephone
01287 612629
Case Officer Email
claire.griffiths@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
12/02/2021
Date Valid
18/02/2021
Expiry
21/05/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
21/05/2021
Decision Level
Delegated

Conditions table
# Condition Details
1 Development shall not commence beyond site clearance until a detailed scheme for the disposal of foul and surface water from the development hereby approved has been submitted to and approved in writing by the Local Planning Authority in consultation with Northumbrian Water and the Lead Local Flood Authority. Thereafter the development shall take place in accordance with the approved details. REASON: To prevent the increased risk of flooding from any sources.
2 No development including site clearance shall commence until trees shown to be retained in this permission have been protected by fencing or other agreed barriers and the method of construction has been agreed. Any fencing shall conform to the specification as shown in BS 5837:2012 Trees in relation to design, demolition and construction and shall be submitted to and approved in writing by the Local Planning Authority. Such fencing or barrier together with the agreed method of construction shall be maintained during the course of the works on site. REASON: In the interests of the long term health of the trees at this site.
3 No development shall take place until a written scheme of investigation (WSI) for an archaeological watching brief has been submitted to and approved in writing by the local planning authority. The WSI shall include:- • Provision for archaeological monitoring of all works at a depth of more than 300mm below current ground level; • Provision for the observation, recording, interpretation, and dissemination of information by report of all deposits, artefacts or other remains of archaeological interest encountered during the works; • A programme of works and monitoring arrangements, including reasonable notification to the local planning authority of commencement of works; and • Details of staff involvement in carrying out the watching brief, and their qualifications and responsibilities. The development shall be carried out in accordance with the approved WSI. REASON: The site is of archaeological importance.
4 Prior to the first occupation of the development boundary walls and fences shall have been erected in accordance with a scheme that has first been agreed in writing with the Local Planning Authority and shall thereafter be maintained. REASON: In the interests of visual and residential amenity.
5 A landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority prior to the commencement of development. The details shall include size, type and species of plant and indicate the proposed layout and surfacing of all open areas. A programme of work shall also be submitted and implemented in accordance with the approved details. REASON: To reserve the rights of the Local Planning Authority with regard to these matters.
6 Details of materials to be used for all hard surfaces shall be submitted to, and approved in writing by the Local Planning Authority, prior to the commencement of the development and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
7 Details of the external materials to be used in the carrying out of this permission (including samples) shall be submitted to, and approved in writing by the Local Planning Authority, prior to the commencement of development and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
8 Prior to the commencement of development, details shall be submitted to and agreed in writing by the Local Planning Authority, of proposals to provide contractors car parking and material storage within the site. The details approved shall be retained for use until completion of the development unless first agreed in writing with the Local Planning Authority. REASON: In the interest of highway safety.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 968 kb 12/02/2021
Consultee Responses
Consultee response - Northumbrian Water 372 kb 02/03/2021
Consultee response - Strategic Planning (Conservation) 46 kb 05/03/2021
Consultee response - Archaeological Consultant 581 kb 15/03/2021
Consultee response - Engineering Team (Highways) 45 kb 23/03/2021
Consultee response - Strategic Planning (Conservation) 689 kb 13/05/2021
Consultee response - Northumbrian Water 75 kb 14/05/2021
Decision
Compliance Decision Notice 539 kb 21/05/2021
Officer Report
Compliance Officer Report 381 kb 21/05/2021
Supporting Documentation
R/2017/0910/CA Decision Notice 147 kb 12/02/2021
Condition No. 3 - Drainage Scheme 134 kb 12/02/2021
Condition No. 4 - Trees 740 kb 12/02/2021
Condition No. 7 - Boundary Treatment 372 kb 12/02/2021
Condition No. 8 - Landscaping Scheme 353 kb 12/02/2021
Condition No. 10 - Hard Surface Materials 653 kb 12/02/2021
Condition No. 11 - External Materials 361 kb 12/02/2021
Condition No. 12 - Contractors Car Parking and Compound Storage 341 kb 12/02/2021
Condition No. 6 - Archaeology 2139 kb 12/02/2021
Condition No. 11 - External Materials 483 kb 30/04/2021
Condition No. 11 - External Materials 2738 kb 30/04/2021
Condition No. 3 - Drainage Scheme 649 kb 30/04/2021
Consultee Name Date Letter Sent Consultation Expiry Date
Engineering Team (Highways) 18/02/2021 -
Environmental Protection Team 18/02/2021 -
NEAR Ltd (Archaeological Services) 18/02/2021 -
Northumbrian Water Ltd 18/02/2021 -
Northumbrian Water Ltd 30/04/2021 -
Strategic Planning Team (CA & LB) 18/02/2021 -
Strategic Planning Team (CA & LB) 30/04/2021 -