R/2020/0811/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
DISCHARGE OF CONDITION 13 OF PLANNING PERMISSION R/2020/0355/FFM FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND FARMS AND LACKENBY SUBSTATION AND ASSOCIATED TEMPORARY CONSTRU...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Saltburn, Marske and New Marske CP
Applicant
PROJCO3 & SOWFL
Applicant's Address
1 FORBURY PLACE 43 FORBURY ROAD READING RG1 3JH
Agent
ARCUS CONSULTANCY SERVICES LTD
Agent's Address
MR TIM WHEELER SUITE 1C SWINEGATE COURT EAST 3 SWINEGATE YORK YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
22/12/2020
Date Valid
05/01/2021
Expiry
02/03/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
23/02/2021
Decision Level
-

Conditions table
# Condition Details
1 (1) Subject to paragraph (5) below, no stage may commence until, for that stage, final pre-construction survey work has been carried out to establish whether a European protected species is present on any of the land affected, or likely to be affected, by any part of that stage or in any of the trees to be lopped or felled as part of that stage. (2) Where a European protected species is shown to be present, the stage likely to affect the species must not commence until, after consultation with the relevant statutory nature conservation body and the Secretary of State for the Environment, Food and Rural Affairs, a scheme of protection and mitigation measures for that stage has been submitted to and approved by the local planning authority. (3) Each stage which requires a scheme of protection and mitigation measures in accordance with paragraph 2 of this condition must be carried out in accordance with the approved scheme(s). (4) In this condition, European protected species” is a European protected species of animal within the meaning of Part 3 (protection of species) of the Conservation of Habitats and Species Regulations 2017. (5) For the avoidance of doubt, each scheme approved under paragraph (2) of this condition may cover one or more stages. REASON: In the interest of the ecological value and long-term maintenance of the site in accordance with policies SD4 and N4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: To ensure that prior to the commencement of any development activities suitable consideration is given to ecological matters.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Covering Letter 301 kb 22/12/2020
Application Form 1142 kb 05/01/2021
Consultee Responses
Consultee response - Natural England 761 kb 20/01/2021
Decision
Compliance Decision Notice R20200811cd Sofia 167 kb 23/02/2021
Compliance Decision Notice R20200811cd Dogger 167 kb 23/02/2021
Compliance Decision Notice R20200811cd Shared 167 kb 23/02/2021
Officer Report
Compliance Officer Report R20200811cd 119 kb 28/04/2021
Supporting Documentation
Ecological Management Plan 3285 kb 22/12/2020
Protected Species 4598 kb 22/12/2020
Consultee Name Date Letter Sent Consultation Expiry Date
Natural England 07/01/2021 -
Natural Heritage Manager 07/01/2021 -