Location
LAND AT
WESTFIELD WAY
HUMMERSEA HILLS
LOFTUS
Proposal
DISCHARGE OF CONDITIONS 5; 8; 9; 14; 15; 18; 19; 20 & 22 ON PLANNING PERMISSION R/2011/0375/FFM AND VARIED BY R/2019/0738/VC
Application Type
Condition Discharge
Status
Approved
Parish(es)
Loftus CP
Applicant
ESH CONSTRUCTION LTD
Applicant's Address
MR R WILKINSON
UNIT 17B
ASTLEY WAY INDUSTRIAL ESTATE
SWILLINGTON
LEEDS
LS26 8XT
Agent
Nicol Thomas
Agent's Address
RUTH WALKER
HEYSIDE HOUSE BLACKSHAW LANE
ROYTON
OLDHAM
OL2 6NS
Agent's work phone
Agent's email
Case Officer
Mrs H Conti
Case Officer Telephone
01287 612340
Case Officer Email
helen.conti@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
21/12/2020
Date Valid
21/12/2020
Expiry
15/02/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
07/05/2021
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | (5) Details of the external materials to be used in the carrying out of this permission (including samples) shall be submitted to, and approved in writing by the Local Planning Authority, prior to the commencement of development and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials. |
| 2 | (8) Details of materials to be used for all hard surfaces (the use of porous/SUDs type drainage systems is recommended)shall be submitted to and approved in writing by the Local Planning Authority, prior to the commencement of the development and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials. |
| 3 | (9) Notwithstanding the submitted landscaping scheme a revised landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority prior to the occupation of any of the dwellings hereby approved. The details shall include size, type and species of plant and indicate the proposed layout and surfacing of all open areas together with the final treatments to the retaining walls. The use of Prunus species should be avoided. Reference should be made to BS 5837 and the extent of the planting beds and species mix reviewed. A programme of work should also be submitted and implemented in accordance with the approved details. REASON: To reserve the rights of the Local Planning Authority with regard to these matters. |
| 4 | (14) No construction works approved by this permission shall be commenced until a scheme for the provision and implementation of a surface water drainage and regulation system (including a Surface Water Management Plan) based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the development has been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented prior to the construction of any impermeable surfaces draining to the system. REASON: To ensure satisfactory drainage at this site. |
| 5 | (15) Notwithstanding the boundary treatment details submitted prior to the commencement of any development relating to boundary walls/fences and retaining walls details of those new boundary walls/fences and retaining walls shall have been submitted to the Local Planning Authority for approval. The approved details shall include type of materials and be implemented prior to the occupation of any of the dwellings at this site. REASON: In the interests of visual and residential amenity. |
| 6 | (18) Prior to the commencement of development details of a contractor’s compound shall be submitted for approval in writing by the Local Planning Authority. The approved details shall be fully implemented prior to commencement of works and remain until completion of construction/building works at this site. REASON: In the interests of highway safety. |
| 7 | (19) Prior to the commencement of development details of a scheme to prevent the deposit of mud/debris onto the highway shall have been submitted to the Local Planning Authority for approval in writing. The approved details shall be fully implemented prior to the commencement of works and be retained for the period of construction/building works. REASON: In the interests of highway safety. |
| 8 | (20) Prior to the commencement of works details of a traffic management plan shall be submitted to the Local Planning Authority for approval in writing. The approved scheme shall be implemented fully prior to the commencement of the works and shall be retained for the duration of construction/building works. REASON: In the interests of highway safety. |
| 9 | (22) Prior to the commencement of construction of any of the dwellings hereby approved full details of existing and proposed ground levels together with finished floor levels for each of the buildings shall have first been submitted to the Local Planning Authority for approval in writing. The approved details shall be implemented in their entirety. REASON: To ensure a satisfactory form of development. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 04/01/2021 | - |
| Engineering Team (Highways) | 05/03/2021 | - |
| Engineers (Local Lead Flood Authority) | 04/01/2021 | - |
| Environmental Protection Team | 04/01/2021 | - |
| Northumbrian Water Ltd | 04/01/2021 | - |