R/2020/0765/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
DISCHARGE OF CONDITION 6 OF PLANNING PERMISSION R/2020/0355/FFM FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND FARMS AND LACKENBY SUBSTATION AND ASSOCIATED TEMPORARY CONSTRUC...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Saltburn, Marske and New Marske CP
Applicant
PROJCO 3 & SOWFL
Applicant's Address
- 1 FORBURY PLACE 43 FORBURY ROAD READING RG1 3JH
Agent
ARCUS CONSULTANCY SERVICES LTD
Agent's Address
MR TIM WHEELER SUITE 1C SWINEGATE COURT EAST 3 SWINEGATE YORK YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
08/12/2020
Date Valid
08/12/2020
Expiry
02/02/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
02/02/2021
Decision Level
-

Conditions table
# Condition Details
1 (1) No stage may commence until, for that stage, written details of the siting, design, layout and any access management measures for any new permanent or temporary means of access to or from a public highway to be used by vehicular traffic, or any alteration to an existing means of access to or from a public highway used by vehicular traffic, have, after consultation with the highway authority, been submitted to and approved by the local planning authority. (2) No stage may commence until, for that stage, written details identifying the routes and accesses for operational maintenance have, following consultation with the highway authority, been submitted to and approved by the local planning authority. (3) All highway accesses must be constructed, maintained and removed in accordance with the approved details. (4) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this condition may cover one or more stages. REASON: In the interest of highway safety and maintenance to ensure the development complies with policy SD4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The provision of new access points will be required in advance of development commencing where new access points are required.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Covering Letter 498 kb 08/12/2020
Application Form 168 kb 08/12/2020
Consultee Responses
Consultee Response - Strategic Transport 45 kb 15/12/2020
Consultee response - Engineering Team (Highways) 449 kb 26/01/2021
Decision
Compliance Decision Notice R20200765cd Dogger 168 kb 02/02/2021
Compliance Decision Notice R20200765cd Shared 168 kb 02/02/2021
Compliance Decision Notice R20200765cd Sofia 168 kb 02/02/2021
Officer Report
Compliance Officer Report R20200765cd 289 kb 02/02/2021
Supporting Documentation
Highways Access Management Plan Report 350 kb 08/12/2020
Highways Access Management Plan Report - Appendix 2.1 1988 kb 08/12/2020
Highways Access Management Plan Report - Appendix 2.2 1821 kb 08/12/2020
Highways Access Management Plan Report - Appendix 3.1 634 kb 08/12/2020
Highways Access Management Plan Report - Appendix 3.2 296 kb 08/12/2020
Highways Access Management Plan Report - Appendix 3.3 327 kb 08/12/2020
Highways Access Management Plan Report - Appendix 4.1 1497 kb 08/12/2020
Highways Access Management Plan Report - Appendix 4.2 9642 kb 08/12/2020
Highways Access Management Plan Report - Appendix 5.1 470 kb 08/12/2020
Consultee Name Date Letter Sent Consultation Expiry Date
Condition Discharge - David Pedlow 15/12/2020 -
Engineering Team (Highways) 15/12/2020 -
Strategic Transport 15/12/2020 -