Location
LAND AT METALS RECOVERY AREA
NORTH WEST OF PD PORTS; NORTH EAST OF SEMBCORP PIPELINE CORRIDOR AND TEES DOCK ROAD
SOUTH EAST OF FORMER SLEM WASTE MANAGEMENT FACILITY AND SOUTH WEST OF HIGHFIELD ENVIRONMENTAL FACILITY
SOUTH BANK
Proposal
DISCHARGE OF CONDITION 4 ON PLANNING APPROVAL R/2020/0465/FFM FOR DEMOLITION OF EXISTING BUILDINGS/STRUCTURES AND ENGINEERING OPERATIONS ASSOCIATED WITH GROUND REMEDIATION AND PREPARATION OF LAND FOR DEVELOPMENT
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
TEESWORKS (FORMERLY SOUTH TEES DEVELOPMENT CORPORA
Applicant's Address
. . .
C/O AGENT
.
.
.
.
Agent
Lichfields
Agent's Address
MISS KATHERINE SIMPSON
THE ST NICHOLAS BUILDING
ST NICHOLAS STREET
NEWCASTLE UPON TYNE
NE1 1RF
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
02/12/2020
Date Valid
02/12/2020
Expiry
27/01/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
14/01/2021
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | No phase of development hereby approved shall take place until further details which are based upon the recommendations set out in the Phase 2 Environmental Site Assessment (Shallow Soils), Arcadis, August 2020 and the Outline Remediation Strategy, Wood, June 2019 have been submitted to and approved by the Local Planning Authority. These details shall include: • An assessment of deep soils, ground and surface water to further assess the risks to Controlled Waters at the site, and the risks to human health from the vapour intrusion pathway; • A further assessment of the risk to identified surface water receptors from concentrations of CoC identified in groundwater; and • A remediation options appraisal for the loose asbestos fibres identified in the Made Ground on the site. Additional data collection may be needed to support the associated risk assessment/remediation design. REASON: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as it relates to earth works which are often the first works on site and relate to site preparation. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 167 kb | 02/12/2020 | |
| Consultee Responses | |||
| Consultee response - Environmental Protection (Contaminated Land) | 16 kb | 11/01/2021 | |
| Consultee response - Environmental Protection (Contaminated Land) | 193 kb | 13/01/2021 | |
| Decision | |||
| Compliance Decision Notice | 454 kb | 14/01/2021 | |
| Officer Report | |||
| Compliance Officer Report | 316 kb | 14/01/2021 | |
| Supporting Documentation | |||
| Condition 4 - Environmental Site Assessment Part2 | 4043 kb | 02/12/2020 | |
| Condition 4 - Environmental Site Assessment Part1 | 9315 kb | 02/12/2020 | |
| Condition No. 4 - Phase 2 Environmental Site Assessment - Shallow Soils | 166769 kb | 17/12/2020 | |
| Condition No. 4 - Shallow Soils Remediation Options Appraisal and Remediation Strategy report | 4790 kb | 17/12/2020 | |
| Condition No. 4 - Phase 2 EnvironmentalSite Assessment Deep Soils and Controlled Waters | 59398 kb | 17/12/2020 | |
| Condition No. 4 - MPA Area Summary | 1767 kb | 17/12/2020 | |
| Condition No. 4 - Re Use Of Iron Steel Slag Response Letter Final | 181 kb | 17/12/2020 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Environmental Protection Team | 09/12/2020 | - |
| Environmental Protection Team | 18/12/2020 | - |