R/2020/0698/CD

Planning Application Details - Official Consultation has expired.

Location
FAWN COACH ROAD BROTTON TS12 2RB
Proposal
DISCHARGE OF CONDITIONS 3, 4, 5, 6, 7, 8 &, 9 OF PLANNING PERMISSION R/2019/0615/FF FOR ERECTION OF 6 DWELLINGS WITH NEW VEHICULAR ACCESS
Application Type
Condition Discharge
Status
Approved
Parish(es)
Skelton and Brotton CP
Applicant
GANNON DEVELOPMENTS LTD
Applicant's Address
MR LEE GANNON FAWN, COACH ROAD BROTTON TS12 2RB
Agent
GANNON DEVELOPMENTS LTD
Agent's Address
MR LEE GANNON 2 HALEWOOD AVENUE NEWCASTLE UPON TYNE NE3 3QH
Agent's work phone
Agent's email
Case Officer
Mrs C Griffiths
Case Officer Telephone
01287 612629
Case Officer Email
claire.griffiths@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
20/11/2020
Date Valid
02/12/2020
Expiry
27/01/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
27/01/2021
Decision Level
-

Conditions table
# Condition Details
1 Prior to the commencement of development an arboricultural method statement shall be submitted to and approved in writing by the Local Planning Authority. The statement shall include details of root protection measures in accordance with BS 5837 ’Trees in relation to design, demolition and construction’ 2012 and construction techniques for works in close proximity to trees. The measures shall be installed on site prior to works commencement and shall be retained for the construction period. The development shall be completed in accordance with the details included in the method statement. REASON: To ensure the remaining trees on site at adequately protected during the construction phase in accordance with policy SD4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The measures need to be agreed and installed on site before any works to the site start to allow for the protection of the trees.
2 Prior to the commencement of development an ecology checking survey shall be completed and submitted to and approved in writing by the Local Planning Authority. The report shall includes measure to protect, mitigate and enhance ecological interest throughout the site and a phasing plan for the proposed works. The development shall be completed in accordance with the approved details. REASON: To protect, mitgate and enhance the ecological presence on site in accordance with policy N4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: To ensure that adequate mitigation is in place before construction and development starts on site.
3 Development shall not commence until a detailed scheme for the disposal of foul and surface water from the development hereby approved has been submitted to and approved in writing by the Local Planning Authority in consultation with Northumbrian Water and the Lead Local Flood Authority. Thereafter the development shall take place in accordance with the approved details. REASON: To prevent the increased risk of flooding from any sources in accordance with the NPPF and policy SD7 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The condition relates to drainage details which need to be installed on site as part of site preparations.
4 Unless otherwise agreed by the Local Planning Authority in writing, development other than that required to be carried out as part of an approved scheme of remediation must not commence until parts (a) to (c) have been complied with. If unexpected contamination is found after development has begun, development must be halted on that part of the site affected by the unexpected contamination to the extent specified by the Local Planning Authority in writing until condition (e) has been complied with in relation to that contamination. (a) Site Characterisation An investigation and risk assessment, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, whether or not it originates on the site. The contents of the scheme are subject to the approval in writing of the Local Planning Authority. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) an assessment of the potential risks to: • human health, • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, • adjoining land, • groundwaters and surface waters, • ecological systems, • archeological sites and ancient monuments; (iii) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with Environment Agency’s Land Contamination Risk Management Guidance (b) Submission of Remediation Scheme A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. (c) Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. (d) Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of part (a) and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of part (b), which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. (e) Long Term Monitoring and Maintenance A monitoring and maintenance scheme to include monitoring the long-term effectiveness of the proposed remediation over a period of 10 years, and the provision of reports on the same must be prepared, both of which are subject to the approval in writing of the Local Planning Authority. Following completion of the measures identified in that scheme and when the remediation objectives have been achieved, reports that demonstrate the effectiveness of the monitoring and maintenance carried out must be produced, and submitted to the Local Planning Authority. This must be conducted in accordance with Environment Agency’s Land Contamination Risk Management Guidance REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to land contamination details which are often the first works on site and relate to site preparation.
5 Prior to construction of foundations on site a Construction Environmental Management Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide the following; i) The parking of vehicles for site operatives and visitors; ii) Loading and unloading of plant and materials; iii) Storage of plant and materials used in constructing the development; iv) The erection and maintenance of security hoarding including decorative displays; v) Wheel washing facilities; vi) Measures to control the emission of noise dust and vibration during the construction period. vii) A scheme for recycling/disposing of waste resulting from demolition and construction works. REASON: In the interest of neigbour amenity and highways safety and in accordance with policy SD4 of the Redcar and Cleveland Local Plan.
6 Prior to any development above damp proof course details of the external materials to be used in the carrying out of this permission (including samples) shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan.
7 Prior to the construction of the final surface treatment, for any hard surfaced areas, details of the materials to be used shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan.
8 Prior to the first occupation of the development, hereby approved, boundary walls and fences shall have been erected in accordance with a scheme that has first been submitted to and agreed in writing with the Local Planning Authority. The boundary walls and fences shall thereafter be maintained unless the express consent of the Local Planning Authority is given. REASON: To ensure that any boundary treatments would accord with policy SD4 of the Redcar and Cleveland Local Plan by respecting the character of the site and the surroundings and raising no significant adverse impact on neighbouring occupiers.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 167 kb 20/11/2020
Consultee Responses
Consultee response - Northumbrian Water (1) 128 kb 14/12/2020
Consultee response - Environmental Protection (Contaminated Land) 192 kb 23/12/2020
Consultee response - Environmental Protection (Nuisance) 239 kb 24/12/2020
Consultee response - Northumbrian Water (2) 1865 kb 18/01/2021
Consultee response - Engineering Team (Highways) 642 kb 28/01/2021
Decision
Compliance Decision Notice 465 kb 27/01/2021
Officer Report
Compliance Officer Report 390 kb 27/01/2021
Plans
Proposed Site Plan 1197 kb 20/11/2020
Condition 8 - Plot 1 Plans and Elevations 223 kb 20/11/2020
Condition 8 - Plot 2 Plans and Elevations 222 kb 20/11/2020
Condition 8 - Plot 5 Plans and Elevations 222 kb 20/11/2020
Condition 8 - Plot 6 Plans and Elevations 202 kb 20/11/2020
Condition 8 - Plot 3 and 4 Plans and Elevations 220 kb 20/11/2020
Supporting Documentation
Condition 4 - Ecological Appraisal 8509 kb 20/11/2020
Condition 7 - Construction Environment Management Plan 6181 kb 20/11/2020
Condition 3 - Arboricultural Method Statement 2375 kb 20/11/2020
Condition 9 - Road Construction Details 1180 kb 20/11/2020
R/2019/0615/FF Decision Notice 433 kb 25/11/2020
Condition 6 - Phase Two Site Investigation Report 4280 kb 02/12/2020
Condition 6 - Phase One Desk Study Report 14876 kb 02/12/2020
Consultee Name Date Letter Sent Consultation Expiry Date
Engineering Team (Highways) 09/12/2020 -
Environmental Protection Team 09/12/2020 -
Northumbrian Water Ltd 09/12/2020 -