R/2020/0682/CD

Planning Application Details - Official Consultation has expired.

Location
VARIOUS LOCATIONS ALONG EXISTING APPROVED CABLE ROUTE FROM MARSKE BEACH TO LACKENBY
Proposal
DISCHARGE OF CONDITION 9 ON PLANNING APPROVAL R/2020/0355/FFM FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND FARMS AND LACKENBY SUBSTATION AND ASSOCIATED TEMPORARY CONSTRUCTI...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
PROJCO 3 & SOWFL
Applicant's Address
- 1 FORBURY PLACE 43 FORBURY ROAD READING RG1 3JH
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER SUITE 1C SWINEGATE COURT EAST 3 SWINEGATE YORK YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
17/11/2020
Date Valid
17/11/2020
Expiry
05/02/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
03/02/2021
Decision Level
-

Conditions table
# Condition Details
1 Code of construction practice 9. (1) No stage may commence until, for that stage a code of construction practice (“CoCP”) in accordance with the outline code of construction practice has been submitted to and approved by the local planning authority following consultation with both Highways England and the relevant statutory nature conservation body. (2) Each CoCP must include consideration of the following matters, amongst others, during construction of the works— (a) construction noise and vibration management; (b) air quality including dust management; (c) sustainable waste management during construction; (d) traffic management and materials storage on site; (e) water management (surface water and groundwater); (f) the mechanism for the public to communicate with the construction teams, including contact details; (g) land use and agriculture, including the management, excavation and removal of soils, land drainage, land quality and biosecurity; (h) a method statement for the crossing of watercourses; (i) method statements for horizontal directional drilling activities of highways, railways and apparatus in the Wilton Complex; (j) plans for public and private access across the development, including details of the temporary re-routing of public rights of way during the construction of the authorised development including the provision of signage and other information alerting the public to the construction works and any re-routing; (k) management and mitigation of artificial light emissions from construction compounds. (3) For the avoidance of doubt, each CoCP approved under paragraph (1) of this condition may cover one or more stages. REASON: In the interest of neighbour amenity, highways safety and protection of ecology value in accordance with policies SD4 and N4 of the Redcar and Cleveland Local Plan. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as it relates to construction details which are often the first works on site and relate to site preparation.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Covering Letter 449 kb 17/11/2020
Application Form 168 kb 17/11/2020
Consultee Responses
Consultee response - Environmental Protection (Nuisance) 12 kb 07/12/2020
Consultee response - Environmental Protection (Contaminated Land) 33 kb 07/12/2020
Consultee response - Public Rights of Way 448 kb 10/12/2020
Consultee response - Natural England 140 kb 17/12/2020
Consultee response - Engineering Team (Highways) 451 kb 06/01/2021
Decision
Compliance Decision Notice R20200682cd Shared 181 kb 03/02/2021
Compliance Decision Notice R20200682cd Sofia 180 kb 03/02/2021
Compliance Decision Notice R20200682cd Dogger 180 kb 03/02/2021
Officer Report
Compliance Officer Report R20200682cd(1) 216 kb 03/02/2021
Supporting Documentation
Condition 9 - Code of Construction Practice 841 kb 17/11/2020
Condition 9 - Appendix 2.1 Consent Boundaries 2975 kb 17/11/2020
Condition 9 - Appendix 4.1 Noise Complaints Procedure V5.0 Eb 20201113 Issue 209 kb 17/11/2020
Condition 9 - Appendix 4.2 Dust And Air Quality Management Plan V4.0 Eb 20201113 Issue 215 kb 17/11/2020
Condition 9 - Appendix 4.3 Site Waste Management Plan V5.0 Eb 20201113 Issue 385 kb 17/11/2020
Condition 9 - Appendix 4.4 Soil Management Plan V5.0 Eb 202011113 Issue 224 kb 17/11/2020
Condition 9 - Appendix 4.5 Land Quality Assessments 6915 kb 17/11/2020
Condition 9 - Appendix 4.7 Method Statement For Trenchless Installation V3.0 Eb 20201113 Issue 228 kb 17/11/2020
Condition 9 - Appendix 4.6 Method Statement For Crossing Of Watercourses V3.0 Eb 20201113 Issue 183 kb 17/11/2020
Consultee Name Date Letter Sent Consultation Expiry Date
Engineering Team (Highways) 10/12/2020 -
Environmental Protection Team 18/11/2020 -
Natural England 10/12/2020 -
Public Rights of Way 10/12/2020 -