R/2020/0680/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 27 (CODE OF CONSTRUCTION) FOR STAGE 2, 4, 10, 11, 13 & 16 OF TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS SPEC...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
SOFIA OFFSHORE WIND FARM LIMITED
Applicant's Address
MS KIM GAULD - CLARK WINDMILL HILL BUSINESS PARK WHITEHILL WAY SWINDON SN5 6PB
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER SUITE 1C SWINEGATE COURT EAST 3 SWINEGATE YORK YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
17/11/2020
Date Valid
17/11/2020
Expiry
12/01/2021
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
07/01/2021
Decision Level
-

Conditions table
# Condition Details
1 .27.—(1) No stage of the onshore works may commence until a code of construction practice (“CoCP”) in accordance with the outline code of construction practice has been submitted to and approved by the relevant planning authority and as appropriate Highways England, following consultation with the relevant statutory nature conservation body. (2) The CoCP must reflect and ensure delivery of the construction phase mitigation measures included in the environmental statement and must include consideration of the following matters, amongst others, during construction of the onshore works— (a) construction noise and vibration management; (b) air quality including dust management; (c) sustainable waste management during construction; (d) traffic management and materials storage on site; (e) water management (surface water and groundwater); (f) the mechanism for the public to communicate with the construction teams, including contact details; (g) land use and agriculture, including the management, excavation and removal of soils, land drainage, land quality and biosecurity; (h) a method statement for the crossing of watercourses; (i) method statements for horizontal directional drilling activities of highways, railways and apparatus in the Wilton Complex; (j) plans for public and private access across the Order limits, including details of the temporary re-routing of public rights of way during the construction of the authorised development including the provision of signage and other information alerting the public to the construction works and any re-routing; (k) management and mitigation of artificial light emissions.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 168 kb 17/11/2020
Consultee Responses
Consultee response - Environmental Protection (Nuisance) 12 kb 07/12/2020
Consultee response - Environmental Protection (Contaminated Land) 33 kb 07/12/2020
Consultee response - Public Rights of Way 447 kb 10/12/2020
Consultee response - Natural England 142 kb 17/12/2020
Consultee response - Engineering Team (Highways) 448 kb 06/01/2021
Decision
Compliance Decision Notice R20200680cd 183 kb 12/01/2021
Officer Report
Compliance Officer Report R20200680cd 640 kb 12/01/2021
Supporting Documentation
Requirement 27 - Stages 2 4 10 11 13 & 16 20201112 ES TW 145 kb 17/11/2020
Requirement 27 - Code of Construction Practice 841 kb 17/11/2020
Requirement 27 - Appendix 2.1 Consent Boundaries 2975 kb 17/11/2020
Requirement 27 - Appendix 4.1 Noise Complaints Procedure V5.0 Eb 20201113 Issue 209 kb 17/11/2020
Requirement 27 - Appendix 4.2 Dust And Air Quality Management Plan V4.0 Eb 20201113 Issue 215 kb 17/11/2020
Requirement 27 - Appendix 4.3 Site Waste Management Plan V5.0 Eb 20201113 Issue 385 kb 17/11/2020
Requirement 27 - Appendix 4.4 Soil Management Plan V5.0 Eb 202011113 Issue 224 kb 17/11/2020
Requirement 27 - Appendix 4.5 Land Quality Assessments 6915 kb 17/11/2020
Requirement 27 - Appendix 4.7 Method Statement For Trenchless Installation V3.0 Eb 20201113 Issue 228 kb 17/11/2020
Requirement 27 - Appendix 4.6 Method Statement For Crossing Of Watercourses V3.0 Eb 20201113 Issue 183 kb 17/11/2020
Consultee Name Date Letter Sent Consultation Expiry Date
Engineering Team (Highways) 10/12/2020 -
Environmental Protection Team 18/11/2020 -
Natural England 10/12/2020 -
Public Rights of Way 10/12/2020 -