R/2020/0643/CD

Planning Application Details - Official Consultation has expired.

Location
LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION
Proposal
SUBMISSION OF DETAILS FOR REQUIREMENT 18 (PHASING) IN RELATION TO STAGES 5, 6 AND 7 OF TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS SPECIFIED IN PART ...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
Projco 3 and SOWFL
Applicant's Address
DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIMITED AND SOFIA OFFSHORE WIND FARM LIMITED 1 FORBURY PLACE 43 FORBURY ROAD READING RG1 3JH
Agent
Arcus Consultancy Services Ltd
Agent's Address
MR TIM WHEELER SUITE 1C SWINEGATE COURT EAST 3 SWINEGATE YORK YO1 8AJ
Agent's work phone
Agent's email
Case Officer
Mrs T Spence
Case Officer Telephone
01287 612341
Case Officer Email
Teri.Spence@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
05/11/2020
Date Valid
05/11/2020
Expiry
31/12/2020
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
22/12/2020
Decision Level
-

No Conditions Found For This Application

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 167 kb 05/11/2020
Decision
Decision Notice 2020 0643 pdf 268 kb 22/12/2020
Officer Report
Compliance Officer Report R20200643cd Pdf 232 kb 22/12/2020
Superseded
Requirement 18 - Phasing Plan 4663 kb 05/11/2020
Supporting Documentation
Requirement 18 - Phasing Plan 141 kb 05/11/2020
Requirement 18 Onshore Phasing Plan Amended 08 12 2020 4242 kb 08/12/2020