R/2019/0719/CD

Planning Application Details - Official Consultation has expired.

Location
LAND NORTH OF WOODCOCK WOOD AND WEST OF FLATTS LANE NORMANBY
Proposal
DISCHARGE OF CONDITIONS 07; 10; 12; 19 & 26 ON OUTLINE PLANNING APPROVAL R/2016/0326/OOM (GRANTED ON APPEAL REFERENCE APP/V0728/W16/3158336) FOR MEANS OF APPEARANCE, LANDSCAPING, LAYOUT AND SCALE FOR 400 DWELLINGHOUSES
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
MILLER HOMES
Applicant's Address
MR ANDREW WALL CENTRAL BUILDING 26 CARLBURY ROAD AYCLIFFE BUSINESS PARK NEWTON AYCLIFFE DL5 6BH
Agent
MILLER HOMES
Agent's Address
MR ANDREW WALL CENTRAL BUILDING 26 CARLBURY ROAD AYCLIFFE BUSINESS PARK NEWTON AYCLIFFE DL5 6BH
Agent's work phone
Agent's email
Case Officer
Mrs L Hall
Case Officer Telephone
01287 612343
Case Officer Email
Lyndsey.Hall@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
04/12/2019
Date Received
22/11/2019
Date Valid
22/11/2019
Expiry
26/02/2020
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
27/03/2020
Decision Level
Delegated

Conditions table
# Condition Details
1 No development (except for site preparation works and the formation of a site compound) shall take place until full engineering details for site access as shown on plan reference 2057/SK001/006 have been submitted to and approved in writing by the local planning authority. The approved access must be completed prior to the first occupation of any dwelling on site.
2 No development, shall take place until a Construction Environmental Management Plan (CEMP) for the phase(s) has been submitted to and approved in writing by the local planning authority. The approved CEMP shall be adhered to throughout the construction period and shall include details of: i. the methods to be used to control the emission of dust, noise and vibration from construction works, including details of any mitigation measures required; ii. measures to control the deposit of mud and similar debris on adjoining public highways; iii. site fencing and security; iv. temporary contractor’s buildings, plant, storage of materials, lighting and parking for site operatives; v. the use of generators; vi. the routing of all HGV movements associated with the construction phases; vii. arrangements for the turning of vehicles within the site so that they may enter and leave the site in a forward gear; viii. restrictions on burning; ix. pedestrian and cyclist protection throughout construction including the use of the Flatts Lane Bridleway (no. 102/14/1); x. a risk assessment of construction activities with a potentially damaging effect on ecological receptors, existing trees and hedges including measures to identify and protect any such receptors during construction; xi. the location and timing of sensitive work to avoid harm to biodiversity features; xii. roles and responsibilities for the implementation of CEMP requirements and measures.
3 Development shall not begin until a scheme to deal with any contamination of the site has been submitted to and approved in writing by the local planning authority. The approved scheme shall include an investigation and assessment to identify the extent of contamination and the measures to be taken to avoid risk to the public when the site is developed. Development shall not commence until the measures approved in the scheme have been implemented.
4 No development (except for site preparation works and the formation of a site compound) shall take place until a scheme for the incorporation of 35 (open fronted and hole) nesting boxes within areas of retained woodland, 40 nesting boxes suitable to house sparrow and starling incorporated into garages and two owl boxes to be installed on retained trees is submitted to and approved in writing by the local planning authority. The development shall thereafter be undertaken in accordance with the approved details.
5 Prior to the occupation of the 200th unit, a scheme for an artwork feature(s) shall submitted to and approved in writing by the local planning authority. The art feature(s) shall be installed on site in accordance with the approved scheme prior to the occupation of the 350th unit and be maintained throughout the lifetime of the development.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 166 kb 22/11/2019
Consultee Responses
Consultee response - Natural Heritage Manager 38 kb 22/11/2019
Consultee response - Environmental Protection (Contaminated Land) 17 kb 02/12/2019
Consultee response - Environmental Protection (Nuisance) 24 kb 09/12/2019
Consultee response - Engineering Team (Highways) 39 kb 14/01/2020
Consultee response - Environmental Protection (Contaminated Land) (2) 13 kb 27/01/2020
Consultee response - Environmental Protection (Nuisance) (2) 7 kb 27/01/2020
Decision
Compliance Decision Notice 112 kb 27/03/2020
Supporting Documentation
Appeal Decision - R/2016/0326/OOM 244 kb 22/11/2019
Condition No. 12 - Phase 2 Report GeoEnvironmental Appraisal 9066 kb 22/11/2019
Condition No. 19 - Nesting Box Locations 770 kb 22/11/2019
Condition No. 26 - Artwork Proposal 278 kb 22/11/2019
Condition No. 07 & 10 - CEMP 3342 kb 22/11/2019
Condition No. 26 - Artwork Locations 1440 kb 22/11/2019
Consultee Name Date Letter Sent Consultation Expiry Date
Condition Discharge - Claire Griffiths 21/11/2019 -
Engineering Team (Highways) 21/11/2019 -
Environmental Protection Team 23/01/2020 -
Environmental Protection Team 21/11/2019 -
Natural Heritage Manager 21/11/2019 -